CONTENTS
1.4 Summary of Construction Activities
1.5 Summary of EM&A Programme Requirements
1.6 Status of Other Statutory Environmental Requirements
2.1 Environmental Site Inspection
2.3 Implementation Status of Environmental Mitigation Measures
2.4 Summary of Exceedances of the Environmental Quality Performance Limit
2.5 Summary of Environmental Complaints, Notification of Summons and Successful Prosecutions
3....... forecast for the next reporting period
3.1 Works Programme for the Next Reporting Period
3.2 Monitoring Schedule for the Next Reporting Period
4....... Conclusion and recommendations
Annexes
Annex A Project Organisation
Annex B Construction Programme
Annex C Environmental Mitigation Implementation Schedule (EMIS)
Annex D Status of Statutory Environmental Requirements
Annex E Waste Management Checklist
Annex F Waste Flow Table
List of Tables
Table 1.1 Contact Information of Key Personnel
Table 1.2 Major Construction Activities Undertaken in the Reporting Period
Table 1.3 Summary of Status for the EM&A Programme under the Updated EM&A Manual
Table 2.1 Quantities of Waste Generated for FEP-01/558/2018.
Table 2.2 Quantities of Waste Generated and Dredged Marine Sediment for FEP-02/558/2018
Table 2.3 Quantities of Waste Generated and Dredged Marine Sediment for FEP-03/558/2018
Table 3.1 Major Construction Activities for the Next Reporting Period
List of Figures
Figure 1.1 Indicative Location of Key Project Components
Figure 1.2 Location and Works Area of GRS at BPPS
Figure 1.3 Location and Works Area of GRS at LPS
To support the increased use of natural gas in Hong Kong from 2020 onwards, Castle Peak Power Company Limited (CAPCO) and The Hongkong Electric Co., Ltd. (HK Electric) have identified that the development of an offshore liquefied natural gas (LNG) receiving terminal in Hong Kong using Floating Storage and Regasification Unit (FSRU) technology (‘the Project’) presents a viable additional gas supply option that will provide energy security through access to competitive gas supplies from world markets. The Project will involve the construction and operation of an offshore LNG import facility to be located in the southern waters of Hong Kong, a double berth jetty, and subsea pipelines that connect to the gas receiving stations (GRS) at the Black Point Power Station (BPPS) and the Lamma Power Station (LPS). To demarcate the works between different parties, the following Further Environmental Permits (FEPs) were issued for the Project:
§ the double berth jetty at LNG Terminal under the Hong Kong LNG Terminal Limited (HKLTL), joint venture between CAPCO and HK Electric (FEP-01/558/2018);
§ the subsea gas pipeline for the BPPS and the associated GRS in the BPPS under CAPCO (FEP-03/558/2018); and
§ the subsea gas pipeline for the LPS and the associated GRS in the LPS under HK Electric (FEP-02/558/2018).
The construction of the subsea gas pipeline for the BPPS and the associated GRS in the BPPS under FEP-03/558/2018 commenced on 23 September 2020 while the construction works under FEP-01/558/2018 and FEP-02/558/2018 had yet to commence in the reporting period. The commencement dates of construction works for FEP-01/558/2018 and FEP-02/558/2018 are expected to be 27 November 2020 and 13 December 2020, respectively.
This is the Monthly EM&A Report presenting the EM&A works carried out during the period from 23 September to 31 October 2020 for the Project in accordance with the Updated EM&A Manual. A summary of monitoring and audit activities conducted in the reporting period is listed below:
Activities |
Number of Sessions |
For FEP-03/558/2018 |
|
Environmental Site Inspection |
5 |
Environmental auditing works, including regular site inspections of construction works conducted by the ET and audit of implementation of Waste Management Plan were conducted in the reporting period. There were no observations and reminders recorded during the regular site inspections.
Breaches of Action and Limit Levels
Since there were no construction activities conducted in the reporting period requiring impact monitoring of marine water quality and marine mammal in accordance with the Updated EM&A Manual, there were no breaches of action and limit levels.
Environmental Complaints, Notification of Summons and Successful Prosecution
There were no environmental complaints, notification of summons and successful prosecutions recorded in the reporting period.
Reporting Changes
There was no reporting change in the reporting period.
Forecast of Impact Predictions
As informed by the Contractor, construction activities to be undertaken in the next reporting period of November 2020 include the following:
FEP |
Land-based Works |
Marine-based Works |
FEP-01/558/2018 |
§ Nil |
§ Nil (1) |
FEP-02/558/2018 |
§ Nil |
§ Nil |
FEP-03/558/2018 |
§ Preparation works at the new GRS (including set-up of site offices, erection of hoarding and mobilisation of wastewater treatment facilities); § Excavation for Fire Services, oily water and stormwater drainage diversion; and § Excavation for Plate Load Test - Pipe Rack |
§ Nil |
Remark: (1) It is anticipated that the piling installation vessel for construction of the jetty would mobilise in November 2020. Marine-based works for FEP-01/558/2018 are expected to start in December 2020.
Potential environmental impacts arising from the above upcoming construction activities in the next reporting period of November 2020 are mainly associated with dust emission from construction activities and stockpiles, waste management, site surface runoff and wastewater discharge.
To support the increased use of natural gas in Hong Kong from 2020 onwards, Castle Peak Power Company Limited (CAPCO) and The Hongkong Electric Co., Ltd. (HK Electric) have identified that the development of an offshore liquefied natural gas (LNG) receiving terminal in Hong Kong using Floating Storage and Regasification Unit (FSRU) technology (‘the Project’) presents a viable additional gas supply option that will provide energy security through access to competitive gas supplies from world markets. The Project will involve the construction and operation of an offshore LNG import facility to be located in the southern waters of Hong Kong, a double berth jetty, and subsea pipelines that connect to the gas receiving stations (GRS) at the Black Point Power Station (BPPS) and the Lamma Power Station (LPS).
The Environmental Impact Assessment (EIA) Report for the Project was submitted to the Environmental Protection Department (EPD) of the HKSAR Government in May 2018. The EIA Report (EIAO Register No. AEIAR-218/2018) was approved by EPD and the associated Environmental Permit (EP) (EP-558/2018) was issued in October 2018.
An application for Further Environmental Permits (FEP) were made on 24 December 2019 to demarcate the works between the different parties. The following FEPs were issued on 17 January 2020 and the EP under EP-558/2018 was surrendered on 5 March 2020:
§ the double berth jetty at LNG Terminal under the Hong Kong LNG Terminal Limited (HKLTL), joint venture between CAPCO and HK Electric (FEP-01/558/2018);
§ the subsea gas pipeline for the BPPS and the associated GRS in the BPPS under CAPCO (FEP-03/558/2018); and
§ the subsea gas pipeline for the LPS and the associated GRS in the LPS under HK Electric (FEP-02/558/2018).
The location of these components is shown in Figures 1.1, 1.2 and 1.3. The construction of the subsea gas pipeline for the BPPS and the associated GRS in the BPPS under FEP-03/558/2018 commenced on 23 September 2020 while the construction works under FEP-01/558/2018 and FEP-02/558/2018 had yet to commence in the reporting period. The commencement dates of construction works for FEP-01/558/2018 and FEP-02/558/2018 are expected to be 27 November 2020 and 13 December 2020, respectively.
This is the Monthly EM&A Report for the Project which summarises the key findings of the EM&A programme during the reporting period from 23 September to 31 October 2020 for the construction works for the Project in accordance with the Updated EM&A Manual and the requirements of the Further Environmental Permits (FEP-01/558/2018, FEP-02/558/2018 & FEP-03/558/2018).
The organisation structure of the Project is shown in Annex A. The key personnel and contact details are summarised in Table 1.1 below.
Table 1.1 Contact Information of Key Personnel
Party |
Position |
Name |
Telephone |
CAPCO / HKLTL (For FEP-01/558/2018 and FEP-03/558/2018)
|
Senior Environmental Manager |
Dr Helen Chiu |
2596 4116 |
HK Electric / HKLTL (For FEP-01/558/2018 and FEP-02/558/2018)
|
Head of Mechanical Engineering, Projects Division
|
Norman Chan
|
3143 3819
|
Environmental Team (ET) (ERM-Hong Kong, Limited)
|
ET Leader
|
Raymond Chow
|
2271 3114 |
Independent Environmental Checker (IEC) (Mott MacDonald Hong Kong Limited)
|
IEC
|
Arthur Lo
|
2828 5757 |
Contractor (CNOOC Offshore Oil Engineering Co. Ltd.) |
Environmental Manager |
H Y Tang |
6111 5789
|
Environmental Officer |
Kelvin Cheung |
9060 1020 |
The programme of the construction is shown in Annex B.
As informed by the Contractor, details of the major construction activities undertaken in the reporting period are listed in Table 1.2 below:
Table 1.2 Major Construction Activities Undertaken in the Reporting Period
FEP |
Land-based Works |
Marine-based Works |
FEP-01/558/2018 |
Nil |
Nil |
FEP-02/558/2018 |
Nil |
Nil |
FEP-03/558/2018 |
§ Preparation works at the new GRS (including set-up of site offices, erection of hoarding and mobilisation of wastewater treatment facilities). |
Nil |
The environmental mitigation implementation schedule (EMIS) is presented in Annex C.
The status of EM&A Programme for all environmental aspects required under the Updated EM&A Manual are presented in Table 1.3. As no marine-based construction activities (i.e. dredging/jetting operations and piling works) were undertaken in the reporting period, relevant environmental monitoring (i.e. marine water quality monitoring and marine mammal monitoring, including vessel-based line transect surveys and passive acoustic monitoring) were not required to be monitored in accordance with the Updated EM&A Manual. Thus, no Action/Limit Levels were triggered in the reporting period and the actions as specified in the respective Event and Action Plans were not required to be taken.
Table 1.3 Summary of Status for the EM&A Programme under the Updated EM&A Manual
Aspects |
Relevant FEP(s) |
Status |
Water Quality |
||
Baseline Monitoring |
FEP-01/558/2018 FEP-02/558/2018 FEP-03/558/2018 |
§ Completed |
Efficiency of Silt Curtain System |
FEP-02/558/2018 FEP-03/558/2018 |
§ To be implemented upon early stage of construction works for dredging/jetting operations for FEP-02/558/2018 and FEP-03/558/2018 |
Construction Phase Monitoring |
FEP-02/558/2018 FEP-03/558/2018 |
§ To be implemented upon commencement of construction works for dredging/jetting operations for FEP-02/558/2018 and FEP-03/558/2018 |
Post-Construction Monitoring |
FEP-02/558/2018 FEP-03/558/2018 |
§ To be implemented upon completion of construction works for the Project |
Monitoring for Hydrotesting for the Subsea Gas Pipelines |
FEP-02/558/2018 FEP-03/558/2018 |
§ To be implemented during hydrotesting for the subsea gas pipelines |
First-year of LNG Terminal Operation |
FEP-01/558/2018 |
§ To be implemented during LNG Terminal operation |
Maintenance Dredging |
FEP-01/558/2018 |
§ To be implemented during maintenance dredging |
Waste Management |
||
Audit of Waste Management Practice |
FEP-01/558/2018 FEP-02/558/2018 FEP-03/558/2018 |
§ On-going for FEP-03/558/2018 § To be implemented upon commencement of construction works for FEP-01/558/2018 and FEP-02/558/2018 |
Ecology |
||
Baseline Monitoring (Vessel-based Line Transect Survey and Passive Acoustic Monitoring) |
FEP-01/558/2018
|
§ Completed |
Construction Phase Monitoring (Vessel-based Line Transect Survey and Passive Acoustic Monitoring) |
FEP-01/558/2018 |
§ To be implemented upon commencement of construction of the LNG Terminal |
Post-Construction Monitoring (Vessel-based Line Transect Survey and Passive Acoustic Monitoring) |
FEP-01/558/2018 |
§ To be implemented upon completion of construction works for the Project |
Marine Mammal Exclusion Zone Monitoring |
FEP-01/558/2018 FEP-02/558/2018 FEP-03/558/2018 |
§ To be implemented when percussive piling works for construction of Jetty (under FEP-01/558/2018) or marine dredging / jetting operations (under FEP-02/558/2018 / FEP-03/558/2018) are undertaken |
Environmental Site Inspection |
||
Regular Site Inspection |
FEP-01/558/2018 FEP-02/558/2018 FEP-03/558/2018 |
§ On-going for FEP-03/558/2018 § To be implemented upon commencement of construction works for FEP-01/558/2018 and FEP-02/558/2018 |
Records of Operating Speeds and Marine Travel Routes for Working Vessels |
FEP-01/558/2018 FEP-02/558/2018 FEP-03/558/2018 |
§ To be implemented upon commencement of marine-based construction works for FEP-01/558/2018, FEP-02/558/2018 and FEP-03/558/2018 |
Environmental Log Book |
FEP-01/558/2018 FEP-02/558/2018 FEP-03/558/2018 |
§ On-going
|
The environmental licenses and permits, including further environmental permits, registration as chemical waste producer, construction noise permits, which were valid in the reporting period are presented in Annex D. No non-compliance with environmental statutory requirements was identified.
The EM&A programme for the Project required environmental monitoring for marine water quality and marine mammals as well as environmental site inspections for air quality, construction noise, water quality, waste management, marine ecology, landscape and visual, and hazard to life impacts. As presented in Section 1.5, environmental site inspections and audit on waste management practice were conducted for FEP-03/558/2018 and the findings are presented below.
Regular environmental site inspections were carried out with the Contractor and Project Proponent to confirm the implementation of appropriate environmental protection and pollution control mitigation measures for air quality, construction noise, water quality, waste management, marine ecology, landscape and visual, and hazard to life impacts under the Project. In the reporting period, five (5) environmental site inspections were carried out at proposed GRS in BPPS for FEP-03/558/2018 on 30 September, 7, 14, 21 and 28 October 2020. The Independent Environmental Checker (IEC) attended the environmental site inspections as the IEC audits on 30 September and 14 October 2020 during the reporting period. There were no observations and reminders recorded during the regular site inspections. The environmental mitigation implementation schedule (EMIS) is presented in Annex C.
Waste management audits were performed with reference to the Waste Management Checklists for the corresponding Waste Management Plans detailed in Annex E during the regular environmental site inspections carried out in the reporting period. No non-compliance for Contractor’s waste management practices was identified during the audits.
The quantities of different types of waste generated and dredged marine sediment for the three FEPs are summarised in Tables 2.1, 2.2 and 2.3 with reference to the waste flow tables prepared by the Contractor. No waste was generated in the reporting period. A detailed waste flow table is presented in Annex F.
Table 2.1 Quantities of Waste Generated for FEP-01/558/2018
Inert C&D Materials Generated (in ‘000m3) |
||||||
Month/Year |
Total Quantity Generated |
Hard Rock and Large Broken Concrete |
Reused in the Contract |
Reused in other Projects |
Disposed as Public Fill |
Imported Fill |
Sept 2020 |
0 |
0 |
0 |
0 |
0 |
0 |
Oct 2020 |
0 |
0 |
0 |
0 |
0 |
0 |
C&D Wastes Generated |
||||||
Month/Year |
Metals (in ‘000kg3) |
Paper / Cardboard Packaging (in ‘000kg3) |
Plastics (in ‘000kg3) |
Chemical Waste |
Other (e.g. general refuse) (in ‘000m3) |
|
(in ‘000kg3) |
(in ‘000L) |
|||||
Sept 2020 |
0 |
0 |
0 |
0 |
0 |
0 |
Oct 2020 |
0 |
0 |
0 |
0 |
0 |
0 |
Table 2.2 Quantities of Waste Generated and Dredged Marine Sediment for FEP-02/558/2018
Inert C&D Materials Generated (in ‘000m3) |
||||||||||
Month/Year |
Total Quantity Generated |
Hard Rock and Large Broken Concrete |
Reused in the Contract |
Reused in other Projects |
Disposed as Public Fill |
Imported Fill |
||||
Sept 2020 |
0 |
0 |
0 |
0 |
0 |
0 |
||||
Oct 2020 |
0 |
0 |
0 |
0 |
0 |
0 |
||||
C&D Wastes Generated |
||||||||||
Month/Year |
Metals (in ‘000kg3) |
Paper / Cardboard Packaging (in ‘000kg3) |
Plastics (in ‘000kg3) |
Chemical Waste |
Other (e.g. general refuse) (in ‘000m3) |
|||||
(in ‘000kg3) |
(in ‘000L) |
|||||||||
Sept 2020 |
0 |
0 |
0 |
0 |
0 |
0 |
||||
Oct 2020 |
0 |
0 |
0 |
0 |
0 |
0 |
||||
Marine Sediment Dredged (in ‘000m3) |
||||||||||
Month/Year |
Total Quantity of Type L Generated |
Total Quantity of Type M Generated |
Reused in the Contract |
Reused in other Projects |
||||||
Sept 2020 |
0 |
0 |
0 |
0 |
||||||
Oct 2020 |
0 |
0 |
0 |
0 |
||||||
Table 2.3 Quantities of Waste Generated and Dredged Marine Sediment for FEP-03/558/2018
Inert C&D Materials Generated (in ‘000m3) |
||||||||||
Month/Year |
Total Quantity Generated |
Hard Rock and Large Broken Concrete |
Reused in the Contract |
Reused in other Projects |
Disposed as Public Fill |
Imported Fill |
||||
Sept 2020 |
0 |
0 |
0 |
0 |
0 |
0 |
||||
Oct 2020 |
0 |
0 |
0 |
0 |
0 |
0 |
||||
C&D Wastes Generated |
||||||||||
Month/Year |
Metals (in ‘000kg3) |
Paper / Cardboard Packaging (in ‘000kg3) |
Plastics (in ‘000kg3) |
Chemical Waste |
Other (e.g. general refuse) (in ‘000m3) |
|||||
(in ‘000kg3) |
(in ‘000L) |
|||||||||
Sept 2020 |
0 |
0 |
0 |
0 |
0 |
0 |
||||
Oct 2020 |
0 |
0 |
0 |
0 |
0 |
0 |
||||
Marine Sediment Dredged (in ‘000m3) |
||||||||||
Month/Year |
Total Quantity of Type L Generated |
Total Quantity of Type M Generated |
Reused in the Contract |
Reused in other Projects |
||||||
Sept 2020 |
0 |
0 |
0 |
0 |
||||||
Oct 2020 |
0 |
0 |
0 |
0 |
||||||
A summary of the Environmental Mitigation Implementation Schedule (EMIS) is presented in Annex C. The necessary mitigation measures were implemented properly for the Project.
Since there were no construction activities conducted in the reporting period requiring impact monitoring of marine water quality and marine mammal in accordance with the Updated EM&A Manual, there were no breaches of action and limit levels.
Cumulative statistics on exceedance is provided in Annex G.
There were no environmental complaints, notification of summons and successful prosecutions recorded in the reporting period.
Statistics on environmental complaints, notification of summons and successful prosecutions are summarised in Annex G.
Construction activities to be undertaken in the next reporting period of November 2020 are summarised in Table 3.1 below, together with the key issues:
Table 3.1 Major Construction Activities for the Next Reporting Period
Activities |
Key Issues |
Under FEP-01/558/2018 |
|
Marine-based Works |
|
§ Nil (1) |
§ N/A
|
Under FEP-02/558/2018 |
|
Land-based Works |
|
§ Nil |
§ N/A |
Marine-based Works |
|
§ Nil |
§ N/A
|
Under FEP-03/558/2018 |
|
Land-based Works |
|
§ Preparation works at the new GRS (including set-up of site offices, erection of hoarding and mobilisation of wastewater treatment facilities) § Excavation for Fire Services, oily water and stormwater drainage diversion § Excavation for Plate Load Test - Pipe Rack |
§ Dust emission from construction activities and stockpiles § Waste management § Site surface runoff and wastewater discharge |
Marine-based Works |
|
§ Nil |
§ N/A |
Remark: (1) It is anticipated that the piling installation vessel for construction of the jetty would mobilise in November 2020. Marine-based works for FEP-01/558/2018 are expected to start in December 2020.
The ET will keep track on the construction activities to confirm compliance of environmental requirements and the proper implementation of all necessary mitigation measures.
As no marine-based construction activities (i.e. dredging/jetting operations and piling works) are planned to be undertaken in the next reporting period, marine water quality monitoring and marine mammal monitoring (vessel-based line transect surveys and passive acoustic monitoring) are not scheduled to be undertaken for the next reporting period of November 2020.
This Monthly EM&A Report presents the key findings of the EM&A works during the reporting period from 23 September to 31 October 2020 for the construction works for the Project in accordance with the Updated EM&A Manual and the requirements of the Further Environmental Permits (FEP-01/558/2018, FEP-02/558/2018 & FEP-03/558/2018).
Environmental auditing works, including regular site inspections of construction works conducted by the ET and audit of implementation of Waste Management Plan were conducted in the reporting period. There were no observations and reminders recorded during the regular site inspections.
There were no environmental complaints, notification of summons and successful prosecutions recorded in the reporting period.
The ET will keep
track on the construction works to confirm compliance of environmental
requirements and the proper implementation of all necessary mitigation
measures.