|
|
|
|
CONTENTS
1.2 Purpose
of the Safety Management Plan
1.3 Structure
of the Safety Management Plan
2....... Safety
Management System
2.8 Accident
/ Incident Investigation
2.10 Evaluation and
Control of Services Providers
2.13 Safety and Health
Awareness
2.14 Accident Control and
Hazard Elimination
2.15 Occupational Health
Assurance Programme
2.16 Communication and
Safety Promotion
3....... Key
Safety Design Features
3.2 Jetty
Monitoring and Management System
3.3.7 Clean
Agent Fire Extinguishing System
3.5 CCTV and
Surveillance System
3.8 Weather
Forecast and Warning System
4....... Operation
and Maintenance (O&M) Procedures
4.2 High
Level Information of O&M Manual
4.3 Reference
to the O&M Manual
5....... Emergency
Response Procedures
5.1 Emergency
Team Organisation and Responsibility of Key Persons
5.8 High
Level Security Control Measures
6....... Marine
Safety Arrangement and Procedures
6.2 Safety
Zone and Marine Control Zone
6.2.1
Necessity for establishing the MCZ in addition to the SZ
6.2.3
Restrictions within
these Zones
6.2.4
Management and Control
Measures of these zones
6.2.5
Implementation of these
zones under the Hong Kong Maritime Framework
6.3 Operational
Arrangement and Procedures for Adverse Weather and Met-ocean Conditions
7....... Regular
Safety Review and Audit
7.1 Collection
of Information on the Safety Management System
7.2 Assessment
and Verification of Information
7.3 Consideration
of Improvements
7.4 Appointment
of Safety Reviewer and Auditor
7.5 Safety
Review Report and Safety Audit Report 42
Annexes
Annex A-1
Determination of Restriction Zones for the LNG Terminal
Annex
A-2 Specifics of Standby
Vessels for Management of the Safety Zone and Marine Control Zone
List of Tables
Table 2.1 FSRU
Terminal HK Key Roles and Responsibilities
Table 4.1 Summary
of Safety and O&M Reference Manual 22
Table 5.1 Summary
of Key Roles and Responsibilities of FIT
List of Figures
Figure
1.1 Indicative Location of Key Project
Components
Figure
2.1 HKLTL Safety Organisation Chart
Figure
2.2 FSRU Terminal HK Organization Chart
(LNG Terminal Operations)
Figure
2.3 Work Flow for Investigation &
Reporting
Figure
5.1 HKLTL Emergency Management Team
Figure
5.2 Terminal First Intervention Team (FIT)
Figure
6.1 Indicative Proposed Marine Transit
Routes
Figure
6.2 Graphical Illustration of Safety Zone
and Marine Control Zone
Figure
6.3 Navigation Simulation Illustration of a
Strayed Vessel from the Dangan Channel
Figure
6.4 Flow Chart of Communication
To support the increased use of natural gas in Hong
Kong from 2020 onwards, Castle Peak Power Company Limited (CAPCO) and The
Hongkong Electric Co., Ltd. (HK Electric) have identified that the development
of an offshore liquefied natural gas (LNG) receiving terminal in Hong Kong
using Floating Storage and Regasification Unit (FSRU) technology (‘the Hong
Kong Offshore LNG Terminal Project’) presents a viable additional gas supply
option that will provide energy security through access to competitive gas
supplies from world markets. The Project will involve the construction
and operation of an offshore LNG import facility to be located in the southern
waters of Hong Kong, a double berth jetty, and subsea pipelines that connect to
the gas receiving stations (GRS) at the Black Point Power Station (BPPS) and
the Lamma Power Station (LPS). The location plan is shown in Figure 1.1.
The Environmental Impact Assessment (EIA)
Report for the Project was submitted to the Environmental Protection Department
(EPD) of the Hong Kong Special Administrative Region Government in May 2018.
The EIA Report (EIAO Register No. AEIAR-218/2018) was approved by EPD and the
associated Environmental Permit (EP) (EP-558/2018) was issued in October
2018. An application for Further Environmental Permits (FEP) was made on
24 December 2019 to demarcate the works between the different parties. The
following FEPs were issued on 17 January 2020 and the EP
under EP-558/2018 was surrendered on 5 March 2020:
§ the double berth jetty at LNG Terminal under
the Hong Kong LNG Terminal Limited, joint venture between CAPCO and HK Electric
(FEP-01/558/2018/A) ([1]);
§ the subsea gas pipeline for the BPPS and the
associated GRS in the BPPS under CAPCO (FEP-03/558/2018/B) ([2]); and
§ the subsea gas pipeline for the LPS and the associated
GRS in the LPS under HK Electric (FEP-02/558/2018/A) ([3]).
In accordance with Condition 4.2 of the FEP of
the LNG Terminal (FEP-01/558/2018/A) (‘the Project’):
FEP No. FEP-01/558/2018/A, Condition 4.2: “The Permit Holder shall, no later than 3 months before the commencement of operation of the Project, deposit with the Director 3 hard copies and 1 electronic copy of a safety management plan for the operation of the Project. The safety management plan shall describe the safety management system (SMS) for the operation of the Project and shall include but not limited to information relating to the key safety design features, operation and maintenance procedures, emergency response procedures, marine safety arrangements and procedures and regular safety audit for the operation of the Project. The safety management plan shall also include the delineation, control and implementation details of a marine safety zone around the jetty for the operation of the Project and the operational arrangements and procedures for adverse weather and met-ocean conditions. The Permit Holder shall fully and properly implement the safety management measures in the deposited safety management plan during operation of the Project.” |
As stated in Condition 4.2 of the FEP of the LNG Terminal
(FEP-01/558/2018/A), this Safety Management Plan presents the safety management
system (SMS) for the operation of the Project, including information relating
to the key safety design features, operation and maintenance procedures,
emergency response procedures, marine safety arrangements and procedures and
regular safety audit for the operation of the Project. In addition, the
delineation, control and implementation details of a marine safety zone around
the jetty for the operation of the Project and the operational arrangements and
procedures for adverse weather and met-ocean conditions are described.
The remainder of this Safety Management Plan is
set out as follows:
§ Section 2 presents the safety management
system for the operation of the Project;
§ Section 3 describes the key safety design
features of the LNG Terminal;
§ Section 4 details the operation and
maintenance (O&M) procedures of the Project;
§ Section 5 presents the emergency response
procedures;
§ Section 6 presents the marine safety
arrangement and procedures; and
§ Section 7 presents the mechanism for regular
safety review and audit.
HKLTL is the owner of the HKOLNG Jetty. HKLTL cares for the safety
and health of our staff, contractors, customers and the public, therefore, in
order to ensure Zero Harm in our workplace and everyone goes home safely, it
aims to achieve zero exposure at all of our work locations including:
§ Eliminate exposures which may lead to serious
injuries and fatality;
§ Uphold safety and health as an integral part of
our work and a value that is never compromised;
§ Develop a proactive, positive and
interdependent team safety culture amongst our staff and contractors, such that
everyone works safely and support each other, and issues are communicated
openly, fairly and with mutual respect;
§ Provide a safe and healthy environment for all
who work on or visit HKLTL’s premises;
§ Use Plan-Do-Check-Act approach to proactively
manage safety and health as an integral part of our work processes and
activities, including the demonstration of innovative ways to improve the
safety management;
§ Comply with the requirements of all applicable
safety and occupational health laws and regulations;
§ Define clear accountability and responsibility
for safety at all levels of the organization, reinforcing the idea that
everyone working for the Project has a responsibility to work safely.
Management must lead by example and provide continued and visible support to
safety;
§ Continuously enhance the knowledge, competence,
awareness and behaviour of the management team, our staff and contractors in safety
and hazard management, through sharing and exchanging knowledge and experience;
§ Actively pursue continuous improvements on
safety performance through executing targeted, defined safety initiatives and
establishing challenging measurable objectives and targets while regularly
reviewing performance;
§ Execute “Fair and Just Culture”; and
§ Nurture an off-the-job safety and health
culture.
Together the Jetty and FSRU Vessel are managed
by MOL FSRU TERMINAL (HONG KONG) Limited, below namely FSRU Terminal HK, which
is the operations & management company based in Hong Kong.
FSRU Terminal HK aspire to be Hong Kong’s most
admired LNG jetty operations and maintenance services company and believe that
this ambition can only be achieved by living and acting according to values
that speak to the economic, social, and environmental responsibilities of
business and society.
The Safety Policy of the Project is:
§ Protection of the environment, the safety and health
of MOL FSRU Terminal Hong Kong’s employees, customers, suppliers and all those
involved is an integral part of our activities;
§ MOL FSRU Terminal Hong Kong
a.
is committed to continuous
improvement in the processes to manage safety, health and environmental
performance;
b.
will contribute to the
continuity of the company by the systematic control, prevention and elimination
of hazards. We will continuously work towards the goals of zero incidents and
no damage to the environment; and
c.
will strictly adhere to
safety, health and environmental governing regulations as a minimum.
§ Line Management’s responsibility is to
demonstrate visible commitment, enforcement and provision of appropriate
resources to implement FSRU Terminal HK’s Safety, Health, Environment (SHE)
policy; and
§ Safety is everyone’s responsibility, and we
expect every all personnel involved in the MOL FSRU Terminal Hong Kong
operations to contribute to the prevention of accidents by reporting, analyzing
and controlling safety, health and environmental hazards. This will be
supported by efficient and effective training programs, empowerment right to
stop anyone from unsafe act, and the development of annual SHE improvement
plans.
The goals of no accidents, no harm to people, and no damage to the
environment are committed from top down through all levels of HKLTL.
Management shall lead by example, and its commitment to health and safety
should be seen and felt by all employees as genuine and deep.
Leadership Commitment Vision, Values and
Policies are in place and aligned with all personnel. Management expectations
are translated into a management system, working procedures and
instructions. Periodic review is conducted against evolving management
expectations. All health and safety regulatory requirements are complied
with.
HKLTL will take the responsibility to monitor
the overall Health, Safety, Security and Environmental (HSSE) performance of
business under the implementation of the Safety Management System. Other
contractors will produce their own Safety Management Plan.
A Health and Safety Organisation with various
Committees should be established and one that engages people at all levels
involving both contractors and suppliers. Roles and responsibilities,
authorities and accountabilities for each position should be clearly defined,
communicated, understood and implemented.
Health and safety professionals are required to
provide and facilitate overall health and safety effort and give advice on
health and safety matters, while responsibility for health and safety rests
with line management.
Managers should demonstrate active engagement and
enhance ownership and involvement from employees and contractors in health and
safety matters. They motivate the team through recognition and continue to
drive interdependent culture, sustainable health and safety improvements and
health and safety leadership across the organisation.
The overall HKLTL organization chart as illustrated in Figure 2.1 identifies
the reporting hierarchy and lines of communication. Safety is a duty of
all and reporting of safety issues is given among other factors on all
business.
At the LNG Terminal operations level, the FSRU
Terminal HK has established an organization chart to ensure that the job
functions and their interaction are clear to the staff as shown in Figure 2.2.
The FSRU Terminal HK shall establish, implement
& maintain the integrated management system with reference to ISO 9001,
ISO14001, ISO 45001 aspects and other local regulatory requirements on FSRU
Terminal HK process. The key roles and responsibility are presented in Table
2.1.
Table 2.1 FSRU
Terminal HK Key Roles and Responsibilities
Key Roles |
Responsibilities |
General Manager (GM) |
§ Ensure adequate resources for the development, implementation, & improvement of Integrated Management System (IMS) § Responsible to ensure that requests, feedback, and complaints are forwarded to the relevant department and acted upon |
Jetty Safety, Health, Environment and Quality (SHEQ) Manager |
§ Responsible for the overall performance monitoring of the IMS § Report to GM on the status of IMS implementation § Provide HKLTL the monthly HSSE performance report |
Other Jetty Managers/ Supervisors/ Jetty Lead |
§ Lead the implementations of IMS § Encourage their staff to participate in the development and improvement of IMS |
All employees |
§ Implement the IMS § Participate effectively in the consultation of IMS aspects |
The major in-house safety rules are presented
below:
§ No alcohol and drug abuse
o No staff or contractors will be allowed to work
under the influence of alcohol or drugs. Use of possession of illegal
substances is strictly prohibited;
§ Stop work authority
o All staff or contractors may stop a work
activity where a hazardous situation exists;
§ No smoking
o Smoking is strictly prohibited at the LNG
Terminal, except in the designated areas.
All the safety standards, rules and procedures
shall meet the statutory requirements and industry practices and the
contractors shall conduct the yearly review for those standards, rules and
procedures. In addition, they are required to submit to HKLTL for
notification.
The FSRU Terminal HK shall provide in-house
safety training related to all activities / tasks with natural gas safety at
the LNG Terminal and safety induction training to staff, contractors and other
visitors who are visiting the LNG Terminal. According to Permit-to-work
System, the natural gas safety training should cover all levels of individual
frontline workers, competent supervision, authorization and
auditing. Moreover, marine and vessel operation safety training
should be included in the safety training programme according to international
practices.
The training plan includes the following major
elements.
§ Theoretical training and the LNG Terminal
description:
o General safety induction;
o Basic LNG training (e.g. terminal design,
operation, process and utilities and a basic understanding of the equipment and
systems installed in the plant, describing their functionality and
characteristics).
§ Safety, Health and Environment (SHE) training:
o All specific aspects of safety from the
specific product (e.g. LNG) environment;
o Terminal safety and emergency procedures with
the aim of preventing the occurrence of any situations which might pose a
hazard to people, environment and the offshore jetty.
§ Procedures training:
o Get familiarized with the work instructions, procedures
and equipment (e.g. start, stop, draining, purging, venting, cool down or
emergency response of the equipment).
§ Vendor training - theoretical and practical:
o Emergency diesel generator, typhoon generator,
fire service generator;
o Fire water pump, fire monitor & foam
system;
o Instrumentation & control;
o Telecommunication system.
§ On-the-job training during commissioning and
operation:
o Practical knowledge about the equipment and the
overall functioning of the jetty facility.
§ Any other training based on statutory and
regulatory requirements:
o HKSAR laws and regulations require (part of)
the Jetty team to be certified and/or qualified in order to be allowed to
perform certain work activities (e.g. confined space, crane, radar, first aid,
abrasive wheel operation, green and blue cards, etc.).
Refresher training frequency is also identified
in the safety training programme. Hence, each employee / contractor
involved in operating a process to assure that they understand and adhere to
the current operating procedures of the process.
Routine inspections are required for major
process units and equipment, such as pressure vessels, storage tanks, piping
systems, relief and vent systems, emergency shutdown (ESD) systems, control
systems (e.g. monitoring devices and sensors), and pumps to ensure the
mechanical integrity of the component meets requirements.
Identify inspection and testing procedures in
alignment with manufacturer’s requirements and recommendations by Mechanic for
pneumatic / mechanical type and Registered Electrical Worker for electrical
equipment including:
§ Qualifications for inspection and testing
personnel;
§ Frequency of inspection and testing for various
types of tools and equipment.
Regular workplace inspections should be
conducted to monitor site health and safety performance. Prior to
approval, a visual inspection is conducted for the worksite to identify any
overlooked problems. The work site must be inspected daily before a
permit to work can be issued. Aside from confirming that all work permit
requirements have been fulfilled, this check is essential to identify any
remaining hazards and to see that the threat they pose are controlled or
eliminated.
Hazards during inspections to be aware of
including the following but not limited to:
§ Residual flammable material;
§ Adequacy of isolation;
§ Radioactive sources;
§ Loose or poorly supported materials/equipment
overhead;
§ Sharp objects; and
§ Drains are covered or enclosed.
The work site must always be inspected by a
competent person before the permit is issued to ensure that conditions are safe
and have not materially changed.
All inspections and tests need to be
well-documented and must follow documented procedures.
Hazardous process would be covered under the
scope of the process safety management system, which focuses on providing
sufficient controls and/or redundancies to avoid a set of conditions that can
lead to process safety incidents.
The FSRU Terminal HK Process Safety Management
framework covers the following major elements:
§ Process Safety Information (PSI);
§ Process Hazard Analysis (PHA) & Risk
assessment;
§ Operating Procedures;
§ Management of Change;
§ Mechanical Integrity and Reliability;
§ Pre-Startup Safety Review (PSSR);
§ Training;
§ Employee Participation;
§ Compliance Audit;
§ Permit to Work (PTW).
It is essential for risks to be eliminated or
reduced "at source". If a risk cannot be controlled completely
by engineering measures, it is necessary to protect the employees by
administrative control or personal protection. The control of hazards and
reduction of risks can be accomplished by following the hierarchy of control
methods. These control measures are not usually mutually exclusive, e.g.
engineering controls can be implemented together with administrative controls like
training and safe work procedure.
Personal Protective Equipment (PPE) programme is required for all work
activities, including marine transportation, to protect personnel from hazards
to be encountered. The PPE Standard would be adopted from the
recommendation by Marine Department (MD) and Labour Department (LD) of Hong
Kong.
PPE shall include as appropriate:
§ Head protection;
o Fitted with Y-shape chin strap
o Adopt different colours helmet for
specific position / trade persons
§ Eyes protection;
§ Hearing protection;
§ Respiratory aid;
§ Foot protection;
§ Fall protection;
§ Hand protection;
§ General protective clothing;
o High visibility straps displayed on
the protective clothing / uniform;
o Anti-static protective clothing;
§ Drown prevention.
An incident investigation shall be initiated immediately
following an incident by an investigation team and the investigation team
members shall be appointed by senior management. The work flow for
investigation and reporting is illustrated in Figure 2.3.
The FSRU Terminal HK shall ensure that
responsibilities are assigned, and the scope of the investigation is defined.
The importance of an incident investigation
process is to ensure that:
§ appropriate incident investigation team with
proper training is formed to identify the cause of incident;
§ for potential significant incident, root cause
can be identified;
§ findings and recommendations are effectively
evaluated and corrective actions are implemented;
§ incident sharing with others to prevent
reoccurrence of similar incident etc.
For severe incidents and loss time injury
cases, an accident investigation panel shall be formed for investigation.
The investigation and the associated report
should be normally completed within 1 month from the date of the incident.
Each responsible party shall develop a
well-designed incident investigation report form to provide guidelines for the
investigator. Upon completion of the investigation report, it shall be
reviewed by legal team, if necessary.
The FSRU Terminal HK shall determine the
responsible parties/persons and targeted time frame for implementing each
recommended action and any follow up action plan. A corrective action
classification, tracking and close out system and procedure is required for all
assets.
The FSRU Terminal HK establish, implement, and
maintain a process needed to prepare for and respond to potential emergency
situations. The preparations include:
§ Establishing a planned response to emergency
situations, including the provision of first aid;
§ Providing training for the planned response;
§ Periodically testing and exercising the planned
response capability;
§ Evaluating performance and, as necessary,
revising the planned response, including after testing and, in particular,
after the occurrence of emergency situations;
§ Communicating and providing relevant
information to all workers on their duties and responsibilities;
§ Communicating relevant information to
contractors, visitors, emergency response services, government authorities and,
as appropriate, the local community; and
§ Taking into account the needs and capabilities
of all relevant interested parties and ensuring their involvement, as
appropriate, in the development of the planned response.
The FSRU Terminal HK maintains and retains
documented information on the processes and on the plans for responding to
potential emergency situations, through the establishment of an Emergency
Response Plan. The Emergency Response Plan defines the emergency
organisation, authorities and responsibilities, list of key personnel, internal
and external communication plans, details of emergency services and information
on hazardous materials. In addition, Incident Action Plans are developed
to ensure a planned response to emergency situations.
The Emergency Response Plan has been prepared
under Condition 4.9 of FEP-01/558/2018/A. The Emergency Response Plan is
also documented and made available in the LNG Terminal’s document management
system and the Central Control Room.
The Emergency Response Plan is communicated to
the relevant staff through briefing and training. The Operations teams
are the de-facto emergency responders and are subjected to monthly and
full-scale drills and exercises.
An annual programme of drills and exercises is
established as part of the Annual SHEQ Plan. Relevant information on emergency
response is provided to visitors to the LNG Terminal through the mandatory
safety induction.
A cooperative approach is used to work with
services providers to achieve excellent SHEQ performance.
The FSRU Terminal HK has developed a system to
screen the suitable services providers for tendering, selection criteria will
be developed for the evaluation and selection of contractors, suppliers, etc.
The selection criteria will consider significant aspects such as cost,
technical ability, reputation, and the ability to meet schedule. SHEQ
management will be given an appropriate weighting along with other selection
criteria.
The role to control the execution of the key
safety concern areas are as follows, but not limited to:
§ SHEQ organization;
§ Work planning;
§ Method statements;
§ Risk assessments;
§ Toolbox talks;
§ Permit to work; and
§ Others where appropriate.
Key concerns for services providers during the
execution of the contract include:
§ Goods conformance to the technical
specifications and all applicable laws;
§ SHEQ considerations for delivery of Goods to site,
such as heavy lift required, extra-long/ wide Goods, etc.;
§ SHEQ consideration for installation/ assemble
work required on site.
The FSRU Terminal HK will ensure the SHEQ
performance of the services providers during the implementation of the contract
works will be regularly and systematically monitored according to statutory
requirement and the contract terms (in particular, the safety plan submitted by
the contractor) to ensure the expected level of SHEQ performance is being
achieved. The evaluation aspects will be considered as follows:
§ accident / incident statistics;
§ summons & convictions;
§ close out of findings from observation;
§ warning / penalty letter / pause work order
received;
§ PPE compliance;
§ observation, near miss reporting & safety
innovation;
§ works in accordance with HKLTL and statutory
standards & requirements;
§ sufficient levels and quality of supervision
etc.
In addition, all safety performance of each
service provider can be discussed and reviewed at the monthly SHEQ Committee
meeting.
The FSRU Terminal HK shall establish monthly
SHEQ Committee meeting to monitor the implementation of the safety management plan
and recommend the company’s SHE policies, standards, compliance requirements,
and performances.
Membership of the Safety Committee comes from
as many levels as practicable and shall include:
§ General Manager (Chairman);
§ Jetty SHEQ Manager (Secretary);
§ Representatives from Managers, Jetty Lead &
Supervisors, field operators of Operations and Maintenance Team; and
§ invited FSRU representative and HKLTL representative,
if relevant (sub) contractors and other staff, as appropriate.
The job-hazard analysis shall determine the
risk to the environment, workers and property. The assessments to
identify the environmental aspects/impacts and health/safety hazards shall be
conducted when there is a change in the terminal operation/process, materials
usage, equipment / machines and new installation.
The following information may be obtained when
conducting the job-hazard analysis:
§ Site plan and work flow;
§ Inputs such as types and quantities of
materials in storage;
§ Outputs such as types and quantities of waste,
fugitive emission, wastewater and nuisance;
§ Process/activity of the work methods for
company’s operations; and
§ Other information such as previous
incidents/accidents / non-compliance, safe work procedure, details of existing
risk control, method of storage, handling and transfer of materials.
The job-hazard analysis team shall identify the
possible health/safety hazards/risks and environmental aspects/impacts covering
the following but not limited to:
§ Injury and fatality;
§ Downtime & operational issues;
§ Damage to property;
§ Short/Long term occupational illness and
ergonomic hazards;
§ Fire & explosion hazards;
§ Implosion hazards;
§ Chemical release;
§ Human behaviour, human capabilities and other
human factors;
§ Air contamination;
§ Water & ground contamination;
§ Hazardous and non-hazardous wastes;
§ Resource depletion; and
§ Aesthetic effects (e.g. noise, odour etc.).
The risk assessment matrix covers the following
two parameters:
§ The likelihood of occurrence of the given environmental
aspect / impact or health/safety hazards; and
§ Consequence (severity of occurrence) of the
environmental effect/Impact or health/safety hazards.
The overall risk rating shall be computed by
multiplying the scores for the two parameters above for the risk
evaluation. Activities with risks rated as Extreme Risk and High Risk
shall not commence until the risk levels have been brought to at least Medium
Risk through additional safeguards or adjustments to the design.
Jetty O&M Managers shall approve all job-hazard analysis for all
routine and non-routine activities.
All job-hazard analyses must be reviewed at
least once every three years or
§ upon any accident, incident, near miss or
dangerous occurrence;
§ when there is any significant change in work
process, products / materials, equipment / machinery, persons or activity;
§ when new information on SHEQ risks is made
known and affecting our operations, such as applicable legal and other
requirements; and
§ corrective action that introduces a new hazard
or changes the hazard.
The Jetty SHEQ Manager shall keep
the latest copy of all job-hazard analyses related to the terminal operations
and maintenance.
Besides, any changes to operating
procedures shall be communicated to the relevant personnel. The operating
procedures and safe work practices shall be reviewed by operations staff every
year to evaluate their relevance and adequacy.
All staff are made aware of:
§ The safety management system policies and
objectives;
§ Their contribution to the improvement of safety
and health performance;
§ The implications and potential consequences of
not conforming to the safety management system requirements;
§ Incidents and the outcomes of investigations that
are relevant to them;
§ Hazards, risks, and actions determined that are
relevant to them; and
§ The ability to remove themselves from work
situations that they consider present an imminent and serious danger to their
life or health, as well as the arrangements for protecting them from undue
consequences for doing so.
The policies are communicated to all staff
during induction, meetings and displayed at accessible areas within the office,
Jetty Control Room and other appropriate means.
All staff are trained on the relevance and
importance of their activities and how they contribute to the achievement of
safety policies and objectives.
All staff are notified of the importance of
safe work and that “no job is so urgent that time cannot be taken to do it
safely”, through the Permit to Work, safety posters and other safety programs.
A risk management process involving the
identification, assessment, and prioritization of risks shall be established.
Risks will be managed until they are eliminated, reduced or controlled to
an acceptable level. Suitable monitoring and control measures to minimize
the probability and/or impact on potential incidents must be in place.
The risk management system aims to identify
hazards, assess probabilities and, consequences as well as determining and
implementing preventive and mitigation measures for managing the risks to As
Low As Reasonably practicable (ALARP) level.
The risk management system shall be composed of
the following elements, but not limited to:
§ Hazard identification;
§ Risk Register;
§ Risk Evaluation;
o Risk assessments are conducted for ongoing
operations, projects / products to identify the potential hazards to personnel,
facilities, public and environment are assessed.
o The risk assessment report would be reviewed
with considering the following areas:
-
Facilities and
operations
-
Schedule and frequency
of assessments
-
The required resources
§ Competence in Risk Assessment;
o a dedicated team composed of members who are
trained in risk management and poses good knowledge of the operation or work
activity to be assessed.
§ Risk controls;
o risk assessment follow-up action plan includes
priority, responsibility and planned timing, and a periodic report is provided
to HKLTL management on the status of action items.
§ Periodic Review.
o Risk owners are properly defined for on-going
monitoring, action taken in mitigating the risks and regular review and
re-assessment.
Occupational Health Assurance Programme is
required to develop for the health concern applied on all personnel in the
HKLTL. Health risks would be identified and mitigated as early as
possible in operation phase by various risk assessments and through the life
cycle of HKLTL. Where applicable, contractor(s) shall produce health
management procedures to cover occupational health issues that workers will be
exposed to.
The Occupational Health Assurance Programmes
including:
§ Pre-employment Medical Examination
o The designated position of terminal staff/
contractors are required to complete a medical declaration and attend a
pre-employment medical examination to ensure that they are fit to work and will
not pose a hazard to themselves or their co-workers;
o Special work groups require employees to
undergo medical examinations in order to comply with statutory requirements and
relevant internal procedures.
§ Health monitoring for specific work groups
o First aiders should be responsible in
monitoring the health status on special work groups from different workforce.
§ COVID-19 Prevention & Control Program
o A COVID-19 Prevention and Control Plan should
be in place;
o This program shall be reviewed periodically as
the threat and risk level of the COVID-19 Epidemic change.
§ Industrial Hygiene Monitoring – Indoor Air
Quality & Illumination
o Specialist should be assigned to check for
working environment monitoring in which the indoor air quality and illumination
set up shall be complied with statutory requirements of the Hong Kong
government.
§ Personal Protective Equipment (PPE)
o PPE programme is required for all work
activities, including marine transportation, to protect personnel from hazards
to be encountered;
o
All types of PPE shall be the
approved type and certified by recognized international code;
o All types of PPE shall be inspected, used,
stored, maintained and replaced in alignment with manufacturer’s requirements
and recommendations and inspection records maintained as required.
Various communication mechanisms and platforms
have been developed to ensure effective and efficient communications are
maintained between FSRU Terminal HK and its stakeholders.
The communication will be documented and
submitted to HKLTL for record purpose. Random checks are conducted by
HKLTL and the selected stakeholders to check on their understanding of
information communicated and timeliness. Various example of communication
including the following, but not limited to:
§ Meetings, e.g. Safety Committee Meeting;
§ Trainings;
§ Workshops;
§ Stand down;
§ Newsletter;
§ Memo;
§ Safety Alert;
§ Safety Moment.
Contractors are required to develop a scheme to
promote the proactive incident prevention involvement together with
HKLTL. Each scheme should have its own specific theme in promoting
different safety aspects. All activities should be recorded and
documented.
The following areas should be covered, but not
limited to:
§ Hand Protection;
§ Observation and Intervention Scheme;
§ Boat Transfer Safety;
§ Offshore Lifting Operation;
§ Smoking Cessation;
§ Drugs and Alcohol Abuse;
§ Health Promotion Day.
The Project has an FSRU Vessel, which will be
moored at the Jetty, providing facilities that enable LNG Carriers (LNGCs) to
deliver cargoes of LNG which will be transferred and stored in the FSRU
Vessel’s LNG storage tanks.
Manual fire protection system actuation
switches are provided on the Fire & Gas System in the FSRU Vessel Control
Room and Satellite Instrument Enclosure for remote actuation of fire
protection. The Fire and Gas Alarm Panel Cabinet (FGAPC) have been
provided on the upper deck of Mooring Dolphin (MD) 1 as per requirement from
the Fire Services Department.
The following safety systems are included in
the FSRU Vessel:
§ Overpressure Protection System:
o The boil-off vapour in the cargo tanks can be
sent to Boil-off Gas (BOG) System to maintain the vapour pressure inside the
cargo tanks. Pressure relief system is also provided for the LNG cargo tanks.
The cargo tank and interbarrier space are fitted with pressure relief valve(s)
which connect to a venting system. The setting of the pressure relief valves
will be lower than the vapour pressure adopted in the design of the cargo
tanks.
§ Navigation System:
o The FSRU Vessel is equipped with advanced
navigational systems such as Digital Global Positioning System (DGPS), radar
and communication system. The marine traffic is monitored by the Vessel Traffic
System (VTS), providing an active monitoring and navigational advice for
vessels.
o The navigation is constantly monitored by well
trained and experienced master and the officers to make good use of the
navigation system for the transit to the LNG Terminal.
§ Double Containment System:
o The containment system is designed as per
international standards including the International Code for the Construction
and Equipment of Ships Carrying Liquefied Gases in Bulk (IGC Code). The
containment system is provided with a full secondary liquid-tight barrier
capable of safely containing all potential leakages through the primary barrier
and, in conjunction with the thermal insulation system, preventing the lowering
of ship structure temperature to an unsafe level.
o Leak detection system is provided between the
primary and secondary containment barriers. In addition, the LNG cargo tanks
are provided with pressure relief valves which connect to a designated vent
piping system.
§ Process Control System:
o Process control valves (e.g. pressure control,
temperature control etc.) are provided in the process facility in order to
continuously maintain the stability of the overall process operation. Process
deviation alarms are also provided to alert the operators to take necessary
actions.
§ Emergency Shutdown (ESD) System:
o ESD System is provided at the FSRU Vessel to stop
LNG flow in the event of an emergency and to return the system to a safe,
static condition so that remedial action can be taken. The ESD system can
be activated automatically through various initiators (e.g. power failure,
cargo tank overfill etc.) and manually through push buttons.
§ Custody Transfer Measurement System (CTMS):
o The FSRU Vessel is provided with an automatic
system for the calculation of LNG and gas volumes in each cargo tank. The
use of such system will facilitate the process of determining quantities
transferred during loading and unloading. The CTMS processes data from
tank level, temperature, pressure sensors, etc. in real time, taking into
account the required corrections and certified gauge table, to produce a
calculation of volumes before, during and after LNG transfer operation.
Overfill protection, vacuum protection and
excess flow protection systems are also installed in the FSRU Vessel.
Jetty monitoring and management system is
provided at the LNG terminal, which serves to closely monitor the mooring line
tension and vessel motion. Excessive mooring line tension and vessel
motion will activate alarm and subsequent ESD system to shutdown the LNG cargo
transfer operation.
The firefighting philosophy for fires involving
LNG/NG is to isolate the source of fuel and allow the fire to continue to burn,
mitigating the consequences and preventing spread/escalation, until the
available fuel has been consumed.
Generally, fire water monitors with deluge
valve are manually activated by the push button on both Jetty Spark Ignition
Engine (SIE) fire alarm system, FSRU Central Control Room (CCR) fire alarm
system, Fire Alarm Mimic Panel at MD1 and site. Fixed clean gas
extinguishing system (NOVEC 1230) can be activated automatically by fire and
gas detection system with 30 seconds time delay and the fire and detection
system on NOVEC 1230 local panel repeat to fire alarm panel on Jetty SIE and
Jetty CCR at FSRU Vessel, as well as activated by manual push button that is
outside the protection room and on the fire and gas control panel both on Jetty
SIE and Jetty CCR at FSRU Vessel.
Flammable gas detectors are located where the
leakage source is nearby and the flammable gas could accumulate. Gas
detection also installed at equipment air intakes such as firewater pump diesel
engines and diesel generator air intakes and inhibit start up if confirmed gas
detected.
Three fire water pumps are provided, one as
duty fire water pump (1x100% on MD4) has a design capacity of 100% of maximum
fire water demand. The other two as standby pumps (2x50% on BD1), each
standby pump has a design capacity of 50% of maximum fire water demand.
During fire conditions, Fire water pump has
been designed to start automatically via fire detection system as well as the
pressure drop in fire water ring main. The fire pumps also can be
activated manually via manual call point located near hydrants as per FSD
requirement.
Two outlets type, non-corrosive metal, hydrants
are installed on the Jetty area for protection not less than every 30 meters.
Each hydrant assembly conforms with Hong Kong local government
requirement. Each outlet of all hydrants shall be instantaneous type
conforming to British Standard (BS) 336 and be individually controlled by a
wheel-operated screw valve designed to open by counter clockwise rotation.
Fire monitors are used for thermal radiation
exposure protection of Jetty equipment. Monitors are constructed from
corrosion resistant material, suitable for seawater use and marine environment.
Deluge valves are activated from the Jetty SIE,
FSRU CCR and Fire Alarm Mimic Panel at MD1 or on site. Push buttons of
deluge valves must be tagged with different fire zone number guide operator to
operate the deluge valves. The firefighting system includes automatic
fire and gas detection systems that shall alert the operators to the presence
of gas release or fire, and continuously monitor detection systems for faults
and system alarms.
Deluge Valve Skids are used for the activation
of fire remote manual operated fire water monitors. Deluge valves are
located at a safe distance from the protected area to avoid damage to the Skid
during fire and explosion. Each deluge system is equipped with manual
bypass valve.
Hose reels are located near the access ways.
The fire water hose reels are provided and can be used to extinguish the
initial fire by non-professional fireman. Hose reels are strategically
located on the Jetty to ensure that every part of the Jetty except jacket
walkway can be reached by a length of not more than 30m.
A total flooding clean agent FK-5-1-12 (NOVEC
1230) fire extinguishing system is provided for each Jetty SIEs, electrical
enclosures, emergency diesel generator enclosure, typhoon diesel generator
enclosure, fire service emergency generator enclosure and firewater pump
enclosures at Breasting Dolphin (BD) 1.
The total flooding clean agent fire
extinguishing systems comply with the requirements of National Fire Protection
Association (NFPA) 2001 and relevant local codes and regulations. A clean
agent fire extinguishing system is provided to protect the area and above the
ceiling as they are not separated by a fire rated partition. Visual and
audible alarm is activated during release of the gas system.
Wheeled dry power extinguisher are provided at
key locations where there is LNG fire risk and step-down transformers.
Wheeled CO2 extinguishers should be located in areas with
electrical hazards such as outside electrical enclosures and near switchgears.
Portable dry chemical fire extinguishers are installed on the entire
Jetty area where there is a fire hazard.
The Jetty is a typical double berth marine
structure that uses mooring / fender facilities to safely moor the FSRU Vessel
and LNGC. The Jetty is designed to be unmanned except during daily/normal
routine inspection and activities such as vessel berthing and Marine Loading
Arm (MLA) connections, preventative/routine maintenance and general operations
attendance.
The design criteria for the boat berthing point
is based on the evaluation whether ship collision impact probability onto
exposed pipeline on MD1 above and below the boat landing. On boat landing
area at MD1 deluge valve activation would also be provided as an alternative
location.
The Jetty
Monitoring and Control system is designed to operate continuously, to
automatically take corrective actions for disturbances caused by changes in
process conditions and to alert the operator on the abnormal conditions of the
unit/plant. If the operating conditions approach the mechanical limits of
the plant equipment or the process parameters exceed defined limits, the plant
ESD system will initiate actions automatically, to bring the plant into a safe
condition.
In the emergency event to facilitate remote
monitoring and status update using CCTV information of the Jetty, HKLTL would
provide necessary support and access to relevant authorities (e.g. Electrical
and Mechanical Services Department (EMSD) as gas safety authority).
The life raft is a lifesaving appliance for
persons in danger when the jetty has some dangerous. The life rafts were
installed on the MD1, MD6, BD1 and BD3.
The escape chute system is used to transfer the
persons from the embarkation station to the platform through the vertical chute
of the system, and then the persons used the life raft to rescue. The escape
chutes were installed on the BD1 and BD3.
The standby vessels (SBV) support the emergency
and maintain a protected perimeter under the Terminal First Intervention Team
coordination. SBV can access and escort external support services for the
emergency, and coordinate with the Jetty Lead. SBV is also available in
case of rescue of man overboard.
Hong Kong has adopted the Tropical Cyclone
Warning Signal regime. Tropical Cyclone Warning Signal T1 is the
universally recognised signal used by the authorities throughout Hong Kong and
is the trigger for ordering pilots, linesman, tugs etc. Prior to Signal
T1 the Terminal management will be monitoring the met ocean forecasts but
Signal T1 becomes the trigger to implement the typhoon departure procedure
which means that the FSRU Vessel will be off the berth before Signal T3 is
hoisted.
Super Typhoons are generally large and intense
storms reach this level in the Pacific Ocean giving ample time for departure
preparation. Super Typhoons should be considered the worst-case scenario
and preparations for departure should be expedited in close consultation with
Hong Kong Observatory (HKO).
Wind speed and direction will be the main
concern, if the sea/swell will not have had time to build to significant
heights/periods for adverse met ocean conditions, other than typhoons.
The HKO raises the Strong Monsoon Signal when a
replenishment of the prevailing monsoon is expected to give rise to mean wind
speeds in excess of 22 knots. This is a regular occurrence during the NE
monsoon, less so for the SW Monsoon. When raised, vessel operators in
exposed waters can expect wind gusts up to 70km/hour (37.8 knots) during the
initial surge with winds declining thereafter until the Signal is lowered.
Sea state will be a major consideration for
small craft and work boats (line handling boats) and will have a bearing on the
decision-making process at the time.
Typhoons and other adverse met ocean events
will be assessed and dealt with on a case-by-case basis in relation to their
potential severity.
HKLTL is the owner of the HKOLNG Jetty. The
terminal is two facilities in one, the FSRU Vessel and the Jetty.
Together the Jetty and FSRU Vessel are managed by the O&M management
company, MOL FSRU Terminal Hong Kong Limited.
The Operations Manager of HKLTL oversees the
O&M of FSRU Vessel and Jetty and is the focal point with FSRU Terminal HK
on O&M. HKLTL will manage the coordination of the facility with the
users and LNG suppliers for the nomination and LNG delivery schedules.
HKLTL O&M mobilization team includes HKLTL
and MOL FSRU Terminal HK for the terminal, led by the Terminal Operations
manager, including engineers and managers from commercial, marine and HSSE.
The O&M mobilization activities focus on:
§ Development of the O&M philosophy;
§ Development of HSE standards for contractors;
§ Defining HKLTL and O&M contractor staffing
requirements;
§ Defining and contracting the O&M contracts
for materials and services considered critical to operations;
§ Organizing proper logistics infrastructures and
marine support base to support the FSRU Terminal HK;
§ Ensuring all the required permits, licenses,
and certifications to operate are in place;
§ Assist contractors to develop O&M budget
and monitoring costs to maximize effectiveness and cost optimization;
§ Ensuring that the right resources are deployed
to support a safe and effective handover of the facilities;
§ Ensuring a safe and effective performance test
in coordination with the contractor/ licensors before provisional acceptance of
the facilities.
Operating procedures shall include for mode of
normal, start up, shutdown, alarm response, foreseeable emergency operations as
well as special operations of operating processes.
The operating procedures should document the safe
work conditions such as operating limit, location of sampling, timing, and
safety precautions in consideration of process safety, occupational safety and
health aspect. Operating procedures shall include the operating limits
resulting from the information specified in the process safety information and
where safety considerations are present, a known-why description of the
following:
§ The consequences of deviation;
§ The steps required to correct or avoid
deviation;
§ Safety systems and their function;
§ Occupational safety and health consideration;
§ Properties of hazardous substances;
§ Special precautions to prevent exposure to
hazards; and
§ Other unique hazards.
A maintenance program must be developed that addresses all safety
related equipment, such as relief devices, temperature and level controllers
and other devices or equipment whose failure could cause a catastrophic
accident.
The mechanical integrity program should include
the following provisions:
§ Categorize list of process equipment,
electrical system and instrumentation for inclusion in the mechanical integrity
programmed;
§ Prioritize the criticality of these equipment
in view of the Occupational Safety & Health and process safety impacts
resulting from equipment failure;
§ Establishment of operating and maintenance
manuals for mechanical, civil, electrical and instrument equipment and devices
that ensure the mechanical integrity of the hardware;
§ List of hardware and indication of their
respective level of safety criticality;
§ The frequency and scope of inspection and
testing;
§ Procedure for inspection and testing,
acceptable limits and criteria for passing the inspection and test;
§ Procedures for equipment defects, maintenance
defects and equipment failure reporting and follow up;
§ Documentation of inspection and test records
and implementation of corrective actions which shall be reported to the
responsible person;
§ System for reviewing changes in tests and inspections
by designated persons;
§ Training of maintenance employees and
contractor workers in the maintenance tasks and ensure they are competent;
§ Part of the mechanical integrity program should
include quality control and assurance system to ensure that the maintenance
materials, spare equipment and parts used in the maintenance meet design
specifications, and any changes in material or equipment parts shall be
appropriately reviewed before use. The system also helps to ensure that proper
materials of construction are used, fabricated and that proper inspection and
installation procedures are carried out; and
§ Reliability analysis on the equipment is
applied in routine maintenance plan to ensure that appropriate intervals of
check, inspection and testing are carried out for both corrosion and erosion
rate of the materials of construction. There should a long-term maintenance for
periodic maintenance of major and critical equipment. Such plan shall be
reviewed annually to take into consideration of the inspection findings,
incident reports and regulatory requirements.
The primary framework of Safety and O&M working
procedures associated with Gas Safety and Safety Management on Jetty are
summarized in Table 4.1.
Table
4.1
Summary of Safety and O&M Reference Manual
Document No. |
Reference Manual |
FSRUHK-SH-001-MA |
Integrated Management System |
FSRUHK-SH-013-PR |
SHEQ Committee Management |
FSRUHK-SH-031-PR |
Safety Observation Round |
FSRUHK-SH-030-PR |
Process Safety Management |
FSRUHK-SH-006-PR |
Compliance with Regulation |
FSRUHK-SH-029-PR |
Control of Work |
FSRUHK-SH-038-PR |
Management of Change |
FSRUHK-OP-007-WI |
Work Instruction - High Pressure Gas Send Out Arms |
FSRUHK-SH-016-PR |
Terminal Emergency Response Plan |
FSRUHK-CM-003-PR |
Contractor Management |
FSRUHK-MA-002-PR |
Inspection and Maintenance Management |
FSRUHK-SH-008-PR |
Performance Measurement and Monitoring |
FSRUHK-SH-042-PR |
Internal Audit Management |
FSRUHK-SH-043-PR |
Management Review |
FSRUHK-SH-041-PR |
Non-Conformance Management |
FSRUHK-SH-040-PR |
Incident Reporting and Investigation |
FSRUHK-SH-033-PR |
Lock out Tag out |
FSRUHK-SH-017-PR |
Fire and Explosion Incident |
FSRUHK-SH-024-PR |
Emergency Response Plan - LNG/Gas Leakage |
FSRUHK-SH-018-PR |
Man Overboard |
FSRUHK-SH-019-PR |
Terminal Emergency Response Plan Hydrocarbon and Chemicals Spillage |
FSRUHK-SH-020-PR |
Personal Injuries |
FSRUHK-SH-021-PR |
Security Event - Bomb Threats |
FSRUHK-SH-022-PR |
Jetty Blackout Start-Up |
FSRUHK-SH-023-PR |
Collision |
FSRUHK-OP-001-MA |
Project Management - Jetty Operations Manual |
FSRUHK-SH-034-PR |
Permit to Work |
FSRUHK-OP-006-WI |
Work Instruction - Unloading Arms Activities, Unloading and Cool Mode |
FSRUHK-OP-011-WI |
Work Instruction - Open Drain System |
FSRUHK-SH-064-PR |
Emergency Departure Plan - Typhoon & Tsunami |
FSRUHK-OP-026-WI |
Work Instruction - Fire Extinguishing Systems |
FSRUHK-SH-048-PR |
Chemical Waste Handling Procedure |
FSRUHK-OP-004-PR |
Defeat of Safety Critical Equipment |
FSRUHK-SH-035-PR |
Working at Heights |
FSRUHK-OP-021-WI |
Work Instruction - Jetty Blackout Start-Up |
FSRUHK-MA-003-MA |
Maintenance Manual |
FSRUHK-SH-039-PR |
Incident Management |
FSRUHK-SH-047-PR |
Garbage Management Procedure |
FSRUHK-OP-035-FO |
SOP for Jetty Typhoon Readiness |
FSRUHK-OP-036-FO |
SOP Jetty Typhoon Readiness for the event of FSRU Reconnection |
FSRUHK-SH-036-PR |
Confined Space Entry Procedure |
FSRUHK-SH-011-PR |
Communication & Meeting Structure |
FSRUHK-SH-101-PL |
SHEQ Plan |
FSRUHK-HR-051-FO |
Competency & Training matrix & schedule |
FSRUHK-SH-049-FO |
Risk Matrix |
FSRUHK-SH-025-PR |
Escape, Evacuation and Rescue |
FSRUHK-SH-026-PR |
Full, Partial and Single Mooring Failure Emergency |
FSRUHK-SH-045-PR |
Personal Protective Equipment Management |
FSRUHK-OP-005-PR |
Alarm Management |
FSRUHK-SH-004-PR |
Business Continuity |
FSRUHK-SH-044-PR |
COVID 19 - Prevention and Control Plan |
The organisation chart of the HKLTL Emergency
Management Team (EMT) is shown in Figure 5.1. The EMT supports the LNG Terminal
Emergency Control Team / Terminal First Intervention Team on technical and
safety expertise if require.
When emergency incidents occur at the Jetty,
the Terminal First Intervention Team (FIT) which is composed of the Jetty FIT,
FSRU Vessel Master and FSRU Crew, is responsible for the execution of the
appropriate emergency procedures as advised by the Jetty Lead, who is the
Incident Controller. The composition of the Terminal FIT is illustrated
in Figure 5.2.
The Terminal Emergency Control Team is
primarily composed of FSRU Terminal HK onshore team members including General
Manager, Duty Manager, O&M Manager, Jetty SHEQ Manager, Maintenance Manager
and Ship Management Company. It will support the terminal FIT and bringing
technical and safety expertise if required.
The Jetty FIT mainly includes the Jetty Lead,
the Shift Supervisor, the Control Room Operator (CRO) and the Field
Operator. The FSRU Vessel Master and FSRU Crew will also be involved if
needed. The responsibilities of each roles in the Jetty FIT is listed in Table 5.1.
Table 5.1 Summary of Key Roles and
Responsibilities of FIT
Key Roles |
Responsibilities |
Jetty Lead |
§ Incident Controller (IC) of FIT; § Assess the emergency severity; § Activate communication protocol in case of accident at the Jetty or at the FSRU Vessel and is the focal point with the government departments if assistance is required; § Monitor and control active and/or passive personnel headcount process. Confirm FSRU personnel headcount with the FSRU Vessel Master; § Coordinate with FSRU Vessel, LNGC, SBV the evacuation of personnel from the place of the incident; § Confirm with the FIT team the operational actions that will be necessary; § Direct all operations without danger to the personnel (FIT, etc.); § Ensure the search for casualties; § Supervise the actions that take place after the emergency; § Use the Public Address General Alarm (PAGA) to declare “All Clear”; and § Restart the operations. |
Shift Supervisor |
§ Support the Jetty Lead. |
Control Room Operator (CRO) |
§ Initiate emergency procedures; § Conduct personnel headcount at the Jetty and update Jetty Lead; § Immediate remote actions to shut down and isolate affected area; § Constant monitoring of the Terminal Safety Systems; § Close communication with FIT: equipment status, process, etc.; § Update Jetty Lead of any potential/escalation or any other impact caused; and § Update Event Log Checklist. |
Field Operator |
§ Support the Jetty Lead. |
FSRU Vessel Master (if needed) |
§ In case of emergency at the FSRU Vessel, inform Jetty Lead and Ship Management Company; § Responsible for the headcount at the FSRU Vessel; § Responsible for on-board operations, life and emergency departure according to Emergency Departure Plan (EDP) |
FSRU Crew (if needed) |
§ Inform FSRU Vessel Master and update the situation; § Assist the FSRU Vessel Master and execute the emergency response procedures. |
All the Jetty personnel including visitors,
contractors, employee are responsible for the following:
§ Must follow emergency procedures in case of
accidents or emergency situations
§ In case of emergency, notifies Jetty Central
Control Room (CCR) with walkie talkie or activate alarm through any manual call
point and follow the instructions given by the Jetty Team;
§ Move to muster points and wait for orders.
The reporting of emergencies may need to inform
HKLTL Terminal Operations Manager, BPPS, LPS and the relevant government
departments.
The emergency contact list includes the
following:
§ CLP – BPPS CCR
§ HK Electric – LPS CCR
§ HKLTL
o Terminal Operations Manager
o SHEQ Manager
o Marine Operations Manager
o Environmental Officer
§ Terminal
o General Manager
o O&M Manager
o Jetty SHEQ Manager
o Duty Manager
o Jetty Operations Manager
o Jetty Lead
o FSRU Vessel Master
§ Government Department
o Fire Services Department
o Environmental Protection Department
o Marine Department
o Hong Kong Police Force
o Electrical and Mechanical Services Department
Fire and explosion hazards at LNG facilities
may result from the presence of combustible gases and liquids, oxygen, and
ignition sources during loading and unloading activities, and/or leaks and
spills of flammable products.
A formal fire response plan supported by the
necessary resources is prepared and provide fire training and response as part
of workforce health and safety induction/training.
Facilities with fire detection and suppression
equipment that meets internationally recognized technical specifications for
the type and amount of flammable and combustible materials should be properly
equipped. A combination of automatic and manual fire alarm systems should
be present. When active fire protection systems are installed, they
should be located to enable rapid and effective response. Fixed systems
may also include foam extinguishers attached to tanks, and automatic or manually
operated fire protection systems at loading/unloading areas.
Two major types of oil spillage are considered:
§ Spill contained at Jetty or on the deck of a
vessel;
§ Spill from Jetty into the marine environment.
When spillage occurs, the first step is to
determine whether it can be handled internally regarding the size of
spill. The second type of oil spillage is considered as the most serious
in terms of the possibility of causing impact to the local cetacean community
and other marine organisms. Upon spillage, hard boom shall be deployed
SBV. The boom will be acted as secondary oil containment (SOC) to enclose
the spillage area to contain the spillage spreading outside.
Ship collision is the structural impact between
two ships or one ship and a floating or still object. Ship Collision
Study for the Terminal project was conducted to review the current local marine
traffic activity around the Jetty.
A Man Overboard (MOB) incident refers to a man
fell overboard while involved in mooring operations. A SBV is available
in case of rescue of man overboard. A man-overboard emergency action plan
is established for the Project.
Personnel have exposure to falls from heights
when working from scaffolding, mobile aerial equipment or permanent / temporary
structure at-height, as well as when they work around unguarded holes and
edges, and over waters.
Staff/ contractors shall make available fall
protection systems per manufacturer’s requirements and recommendations to all
personnel supporting the work at its work sites.
A trained rescue team is required which is
knowledgeable in “suspension trauma” (orthostatic intolerance) and which is
outfitted with fit for purpose emergency rescue equipment located at the work
site.
The International Ship and Port Facility
Security (ISPS) Code would be adopted and implemented for the Jetty
security. Port Facility Security Plan (PFSP) is one of the essential
documents in managing marine security.
The PFSP would be prepared for the business
operation of HKLTL and will be prepared for each designated port facility based
on its security assessment. The Designated Authority is responsible for
examining the security assessments and PFSPs, issuing the Statement of
Compliance and annual audits, and renewing certificates. In compliance
with the ISPS Code, all designated port facilities are required to have
security exercises and drills carried out regularly.
All the marine security arrangement would be
stated in PFSP. The Port Facility Security Officer (PFSO) will confirm
the implementation of appropriate security measures.
In the event of an approaching typhoon,
inclement weather or an emergency situation, it may become necessary for the
FSRU Vessel and/or LNGC where applicable, to depart the LNG Terminal with a
more accelerated timescale than anticipated under normal operational
conditions.
The decision to depart the berth by either the
FSRU Vessel or the alongside LNGC will be dependent on the met ocean forecasts
to ensure adequate margins of safety for all personnel.
International Maritime bodies with an interest
in the provision of safe, competent and efficient Pilotage services worldwide
universally require that adequate time is allocated for the conduct of a
comprehensive Master Pilot Exchange (MPX) on the ship’s bridge prior to the
commencement of active pilotage orders and manoeuvres.
The pilotage arrangement is set out in
accordance with maritime legislation and is primarily on the basis of
navigational safety but also the health and safety of Pilots for boarding.
These pilotage arrangements and marine transit routes are evaluated based on
available meteorological data in relation to operating limits, best industry
practice and inputs from relevant marine studies and assessments to confirm
safe navigation route and the compliance of local regulatory requirements.
As the Project progresses, due to the
associated pilotage arrangement, the marine transit routes of FSRU Vessel and
LNGC have been further discussed with the relevant authorities.
Consequently, the marine transit routes (‘Principal Arrival Route’ and ‘South
Departure Route’) are determined and agreed with the relevant authorities for
implementation to support the operation of the Project. The Principal Arrival
Route for the FSRU Vessel and LNGC will enter HKSAR waters at the due east side
of the existing CEDD’s South Cheung Chau Disposal Ground and will be subject to
the prevailing conditions at the time being. The South Departure Route for the
FSRU Vessel and LNGC with tugs and supporting vessels will need to pass through
the South Lantau Marine Park (SLMP) and then travel to the south to Dangan
Channel. Navigation simulation analysis was conducted to verify the
Principal Arrival Route and South Departure Route based on various constraints
(e.g. water depth, sea conditions, marine traffic, etc). The indicative
Principal Arrival Route and South Departure Route for the FSRU Vessel and LNGC
are presented in Figure
6.1. It should be noted that during the arrival and departure
of the FSRU Vessel and LNGC, there might be adjustment to the proposed marine
transit routes described below to suit the navigation safety and weather
conditions.
Furthermore, it is identified that there could
be optimization of the FSRU Vessel’s departure route (“North Departure Route”)
such that the FSRU Vessel could make use of the new multipurpose anchorage in
the southwest of Lamma Island (i.e. the South Cheung Chau Anchorage) ([4]) for temporary stay during certain events (e.g.
maintenance work at the Jetty ([5]), monsoon, etc.) without crossing Hong Kong
water boundary. With the optimization of the FSRU Vessel’s departure
route, the alternative departure route would allow shorter time for the LNG
Terminal to resume normal operation and services to gas supply to power
stations.
Principal Arrival Route
On arrival in HKSAR waters, the FSRU Vessel /
LNGC will firstly enter Hong Kong waters at the due east side of the existing
CEDD’s South Cheung Chau Disposal Ground for compulsory
pilotage en route to the Jetty with tugs assistance and control.
Other supporting vessels will accompany the FSRU Vessel / LNGC as necessary
along the designated transit route, travelling along north of CEDD’s South
Cheung Chau Disposal Ground and approaching the LNG Terminal. It is
anticipated that during the transit, LNGC with tugs and supporting vessels will
need to pass through the SLMP with a duration of about 30 minutes until
berthing at the LNG Terminal. The FSRU Vessel will not pass through the
SLMP during manoeuvring to the Jetty. However, in the unlikely / emergency
event (e.g. loss of power), the FSRU Vessel with tugs / supporting vessels may
need to pass through the SLMP for safe manoeuvring to the Jetty.
No stopping over or anchoring of
vessels will be necessary during the transit.
South Departure Route
The South Departure Route is the principal route
for the departure of the FSRU Vessel / LNGC. On departure from the LNG
Terminal, the manoeuvres of the FSRU Vessel / LNGC will be executed by the HK
Pilots and captains of FSRU Vessel. Once the ship is clear of the berth and in
a safe position before joining Dangan Channel, the tugs will be let go and the
Pilots disembarked. The departure route as shown in Figure 6.1 for FSRU
Vessel and LNGC with tugs and supporting vessels will need to pass through the
SLMP with a duration of about 30 minutes.
In the unlikely event that this southern
departure route cannot be used (e.g. structural blockage at sea), the FSRU
Vessel / LNGC will need to travel north to follow the same Principal Arrival
Route back to the waters south of Cheung Chau before navigating to Dangan
Channel. It is anticipated that during the transit of FSRU Vessel
and LNGC, both FSRU Vessel and LNGC as well as the tugs and supporting vessels
will need to pass through SLMP with a duration of about 30 minutes until
turning to north of CEDD’s South Cheung Chau Disposal Ground.
North Departure Route
The North Departure Route is the alternative
departure route for the FSRU Vessel, which is the reverse of the Principal
Arrival Route between the LNG Terminal and the South Cheung Chau
Anchorage. This route will make use of the new multipurpose anchorage in
the southwest of Lamma Island (i.e. the South Cheung Chau Anchorage) for
temporary stay during certain events (e.g. maintenance work at the Jetty,
monsoon, etc.) without crossing Hong Kong water boundary. On departure
from the LNG Terminal, the manoeuvres of the FSRU Vessel will be executed by
the HK Pilots and captains of FSRU Vessel. It is anticipated that during
the transit of FSRU Vessel, FSRU Vessel as well as the tugs and supporting
vessels will need to pass through the SLMP with a duration of about 30 minutes
until turning to north of CEDD’s South Cheung Chau Disposal Ground. The
indicative North Departure Route for FSRU Vessel is shown in Figure 6.1.
No stopping over or anchoring of vessels will
be necessary during the transit.
For ship manoeuvres, sufficient tugs will be
used in accordance with the relevant berthing guideline.
For emergency departure situation, as evaluated
from the simulation runs, the critical off-berth conditions of the FSRU Vessel
manoeuvre could be controlled acceptably by the two SBVs. Nevertheless, vessel
manoeuvres for emergency in adverse conditions are subject to the precise tug
development and the wave conditions at the time. Therefore, it is recommended
that Pilots, tug masters and FSRU Vessel /LNGC masters should receive
appropriate training on vessel manoeuvres at the LNG Terminal.
Marine traffic studies and assessments were
also conducted and proposed marine transit routes are recommended as follows:
§ Navigating by pilot for FSRU Vessel and LNGC to
the LNG Terminal via the Principal Arrival Route located between the CEDD’s
South Cheung Chau Disposal Ground and the SLMP is feasible and can maintain a
minimum 2m under keel clearance.
§ No significant hazards or challenges in terms
of boarding pilots, connecting tugs and making a safe approach to the westerly
channel transits when inbound.
§ No significant hazards or challenges in terms
of disconnecting tugs, disembarking pilots and the master being able to make a
safe transit into the Dangan Channel avoiding interfering traffic, when
outbound.
§ Tugs to be used are based on those considered
to be available in the local market, consisting of mixture of 70t and 80t
Bollard Pull (BP) tugs as well as 95t BP standby vessels. Up to 4 tugs will be
used for the operations with option to utilise the SBVs if the Pilot deems it
necessary.
§ Navigation simulation runs demonstrated that
vessels turning into the approach channel can avoid encroaching into CEDD’s
South Cheung Chau Disposal Ground and the SLMP during the turn at the north of
the CEDD’s South Cheung Chau Disposal Ground and subsequent transit of the
channel, except when operating at the western berth or departure using the same
route that the vessels will need to pass through the SLMP boundary with a
duration of less than 30 minutes.
§ Navigation simulation runs demonstrated that
under emergency scenarios of total power and control failure initiated in the
Northern Approach Channel, the Master was able to take control of the vessel,
assisted by tugs, slow down and safely manoeuvre the vessel clear of the LNG
Terminal.
§ The effect of squalls on manoeuvring was also
investigation and the Master was able to control the vessel during a fast
increase in wind speed and reduction in visibility.
In the LNG industry, it is best industry
practice to have zone(s) of varying control measures in order to protect and
maintain the integrity of the LNG Terminal by separating the LNG Terminal’s
operation from other marine users. The LNG Terminal will comprise of both a
Safety Zone (SZ) and a Marine Control Zone (MCZ), see Figure 6.2, which will
limit unauthorised marine activities and personnel and thereby maintain an
acceptable level of safety and security.
Safety Zone
The Safety Zone (SZ) has been
included in the project design as mentioned in the approved EIA Report (EIAO Register No. AEIAR-218/2018)
with a restricted area of 250m (radius from the centre of the Jetty) All access
into the Safety Zone must be authorized by HKLTL in order to not allow any
unauthorized access by vessels or non-essential personnel.
Marine
Control Zone
The Marine Control Zone (MCZ) is
required to mitigate the likelihood of other marine users adversely affecting
the LNG Terminal operations, by limiting speeds and some activities in the near
vicinity of the LNG Terminal. This zone is necessary for the safe berthing and
unberthing of LNGC and the FSRU Vessel. It will also comprise as one of
the control steps to check whether incoming vessels have made advance
arrangement with the operator of the LNG Terminal. A detailed description
of the process to determine these zones is shown in Annex A-1.
In this section, the following
will be explained:
§ The
necessity to establish the MCZ;
§ Sizing
of these zones (250m and 500m respectively);
§ Restrictions
and controlled measures within these zones;
§ How to
manage these zones (e.g. use of SBVs); and
§ How to
implement these zones under the Hong Kong Maritime Framework.
The core reasons for establishing these zones
are:
§ managing
risks from and to the LNG Terminal
§ safe and secured operation of the LNG Terminal
The above drivers for establishing these zones are
in line with international standards and practices for LNG and offshore
facilities, key standards include:
§ EN-ISO-28460:2010
– Petroleum and Natural Gas Industries Installation and Equipment for LNG
Ship-to-Shore Interface and Port Operations
§ The
UK Petroleum Act 1987
§ The Society
of International Gas Tanker and Terminal Operators (SIGTTO) – Floating LNG
Installations – 1st Edition 2021
§ The
IMO ISPS Code
§ IMO’s Convention on the International
Regulations for Preventing Collisions at Sea 1972
In managing risks, the LNG
Terminal is required to meet the risk criteria stipulated in Hong Kong Risk
Guidelines. This is the main driver for establishing the SZ.
However, it was also revealed that SZ alone is not sufficient to ensure the safe
and secured operation of the LNG Terminal, mainly berthing and interferences
with other marine activities. Therefore, there is a need to have a larger
dynamic controlled zone, hence the MCZ.
The dimension of the SZ is
proposed to be 250m from the centre of the Jetty, which is consistent with
industry best practices and guidelines for LNG terminals of a similar
nature. In addition, as assessed the approved EIA Report (EIAO Register No. AEIAR-218/2018), the
individual risk contour of 10-5 per year is within the proposed SZ,
therefore meeting with the respective Hong Kong Risk Guidelines. All access
into the SZ must be authorized by HKLTL in order to not allow any unauthorized
access by vessels or non-essential personnel. Therefore, implementation of this
zone will result in that no public shall be subject to this level of risk, and
also serve to protect other marine users as well as managing the risk to the
LNG Terminal as far as reasonably practical.
Considering the significant size
of the LNG Terminal and FSRU Vessel and the concern of operational safety, a
MCZ of 500m extending from the annulus of the LNG Terminal is to be implemented
to ensure the safe and secured operation of the LNG Terminal as well as the
safety of other marine users/vessels within the vicinity. The main
drivers for establishing MCZ are:
§ Ensure the
LNG Terminal’s operational safety as well as safety of the other marine
users/vessels nearby; and
§ Enhance
the ability of the LNG Terminal to respond to and maintain a sufficient level
of security.
In order to ensure the safe
berthing/unberthing of FSRU Vessel/LNGC, extensive navigation simulations have
been conducted. These simulations have proven the need for an adequate
amount of sea room to allow safe manoeuvring onto the berths at the LNG
Terminal. Therefore, an outer zone from SZ is required to ensure that
marine activities from other users do not impede on such an operation in order
to minimize the risk of collision.
Apart from protecting the berthing/unberthing
operation, the LNG Terminal, being offshore in the HKSAR’s southern boundary,
must monitor potential threats from the flow of traffic in the Dangan Channel
to the South.
This includes planning for and preventing
collision with vessels that have lost propulsion or steerage and are Not Under
Command and potentially on a collision course or drifting into the LNG Terminal
area.
Navigation simulation exercises have been
conducted to check the effectiveness of using the Standby Vessels to deter and intercept
such unauthorised vessels and other intruders. The results show that they are
an effective means of deterrent from such a threat where the simulations
indicated that between 500m to 1000m is sufficient to provide enough clearance
for the interception and preventing the unauthorised vessel entering the SZ. Figure 6.3 illustrates
such navigation simulation of a strayed vessel from the Dangan Channel.
Annex
A-1
provides comparison between the sizes of these zones with other LNG/FSRU
terminals worldwide, it shows that the proposed sizes follow the best practice.
To allow effective management of these zones,
the following measures are proposed:
Restrictions:
§ No
vessels other than those attending the LNG Terminal which are authorised by the
HKLTL shall enter into any part of the SZ and MCZ
§ No
anchoring within the SZ and no unauthorised vessels shall anchor or lie within
the MCZ
§ Restrict
vessel speed to below 6 knots for SZ
§ With
reference to the Marine Parks and Reserves Regulation (Cap. 476A), a speed
limit of below 10 knots would be adopted in line with the adjacent proposed
SLMP for all passing vessels transiting within and in the vicinity of the MCZ
(except the waters within SZ for vessel speed to below 6 knots)
§ Masters,
coxswains and persons-in-charge of all vessels navigating in the vicinity
should keep away from both zones
For the management and control measures of
these zones resides on the following main stakeholders:
§ HKLTL – Hong Kong LNG Terminal Limited, the
owner of the LNG Terminal
§ FSRU Terminal HK – the owner of the FSRU Vessel
and the operator of FSRU Vessel and Jetty
§ HUD – Hongkong United Dockyard, the operator of
SBVs
The daily monitoring and management of these zones
will be controlled by FSRU Terminal HK and FSRU Terminal HK will coordinate
with the SBV’s operator (HUD) for daily operations through visual and electronic (radar,
closed-circuit television (CCTV), automatic identification system (AIS) ([6])) means including the use of night and thermal
vision when required. Remote monitoring via CCTV will be carried out when the FSRU Vessel has
left the berth by the FSRU Terminal HK operator. Remoted monitoring via
electronic guard zones will be conducted by the Standby Vessel operator.
Relevant authorities, e.g. Vessel Traffic Centre (VTC), Hong Kong Police Force
(HKPF) will be sought to
assist in ensuring enough clearance from other non-essential vessels during
berthing of LNGCs or FSRU Vessel where appropriate.
SBV’s, operated by HUD are a key component in
the management of these zones, more details of the roles and responsibilities
of SBVs are detailed in Section 6.2.4.3.
As the owner of LNG Terminal, HKLTL is
responsible for overall safety and security control complying with the
International Ship and Port Facility Security (ISPS) Code under the
International Convention for the Safety of Life at Sea in 2004. The management
approach and control measures of SZ and MCZ are described in the Port Facility
Security Plan (PFSP) under separated submission. MD is responsible for
examining the security assessments and PFSP. Considering security threats and
preventive measures against security incidents, the detail of PFSP is treated
as confidential.
FSRU Terminal HK responds for day-to-day safety
and security operation of the LNG Terminal. She should take all necessary
actions to ensure that all of the requirements / processes of the Port Facility
Security Plan (PFSP) are complied with whilst the jetty facility is
operational.
As part of the implementation of the SZ and
MCZ, the offshore LNG facility will have 2 multipurpose SBVs located in the MCZ
available to monitor the SZ and MCZ.
Having these vessels in attendance additionally
forms a mitigation against the threat of a vessel that is off course (steering
or engine failure). More details of SBVs can be found in Annex A-2.
The main functionality of the SBVs is to assist
the FSRU Vessel and visiting LNGC’s in the event of an emergency situation but
will be routinely patrolling the SZ and MCZ and monitoring/surveillance of the
approaches to the MCZ round-the-clock throughout the year, using visual lookout
from the bridge of the SBV as well as monitoring of local and dedicated marine
VHF radio channels to ascertain the local marine traffic image. Key duties of
the SBVs will include but not limited to the following:
§ Safeguarding the entire area surrounding the
LNG Terminal;
§ Patrolling of SZ and MCZ;
§ Coordination with MD, Fire Services Department
(FSD), Hong Kong Police Force (HKPF) etc. in the event of an emergency;
§ Escort scheduled service vessels attending the
LNG Terminal. FSRU Terminal HK will engage sufficient SBVs for the
monitoring/ surveillance during the period;
§ Monitoring/surveillance of the approaches to
and inside the SZ and MCZ to include but not limited to; real time CCTV, visual
means (night vision, thermal imaging and infrared) and monitoring of electronic
guard zone by marine VHF channels and radar;
§ Performing an initial security sweep of
underside of LNG Terminal prior to FSRU Vessel returning to the Jetty following
an evacuation event;
§ Coordinate and participate in routine security
drills and exercises drills (both internal and multi-Agency);
§ Incident command location for any emergency
related events as directed by the authorities; and
§ Exercises and drills (both internal and
multi-Agency), subject to direction of MD and law enforcement authorities.
It is considered that through the promulgation
of Marine Department Notice (MDN) to disseminate the SZ and MCZ information to
the mariners, while information and advice will be provided through designated
VHF channels to the master.
As aforementioned, the HKLTL will arrange
sufficient SBVs for round-the-clock watch-keeping duties, such that any
approaching vessel if involving potential risk of entering the SZ, MCZ or
developing the risk of collision with the LNG Terminal, would be timely alerted
to change her course to avoid entering into the SZ or MCZ. Hence, a
communication mechanism between the HKLTL, FSRU
Terminal HK, MD and other stakeholders shall be worked out, it will help the
HKLTL and FSRU Terminal HK to discharge their watch-keeping duties.
Depending on the actual situation, MD will take appropriate action to assist marine safety of the LNG Terminal as
far as practicable ([7])([8]).
The communication mechanism shall be developed
for the sake of safe navigation in the SZ, MCZ and the vicinity of the LNG
Terminal. In normal situation, the HKLTL, FSRU Terminal HK, Authorities and
Stakeholders can convey useful information over multiple parties to take
necessary action to adjust or modify the procedure, schedule and planning to
minimize interface conflicts against LNG Terminal operation. If under emergency
incident, the HKLTL and FSRU Terminal HK can facilitate two-way dissemination
or broadcast to multiple parties with the details of an occurring or pending
emergency.
A Jetty CCR, managed by the FSRU Terminal HK, will
operate 24 x 7 throughout the year with real time monitoring of the surrounding
water areas of the LNG Terminal by radar and other detection equipment, as well
as the deployment of two SBVs patrolling the MCZ to handle potential safety
risk, threats and emergency responses.
The FSRU Vessel is fitted with a purpose built
the Jetty CCR where the Duty Control Room Supervisor is in-charge to monitor
the LNG Terminal operations. This Jetty CCR is fitted with a range of
communication devices (VHF/UHF) to communicate with the SBV’s on site and also
fitted with a radar. In addition, the SBV is fitted with Radar and AIS to
monitor vessels in the vicinity of the LNG Terminal.
The Duty Control Room Supervisor will be there
to assist the SBVs in communications in the event of unauthorised intrusions
into the SZ and MCZ and where we need to advise external parties, e.g., MD or
the Marine Police (Marpol) or FSD for any assistance. Communications between
the onsite SBVs is via public or Private VHF Channel, mobile phone or satellite
phone.
The key roles of SBVs include asset protection
from potential vessel collisions and unauthorised intrusions, berthing/
unberthing of FSRU Vessel/ LNGC and/or in the event of adverse weather
conditions and emergency situations.
Furthermore, the Jetty CCR will be responsible
for stakeholder communication and coordination including the jetty, the FSRU
Vessel, LNGC, pilot, harbour tugs, Vessel Traffic Centre (VTC) of MD, Marpol,
FSD, other stakeholders such as the operator of Integrated Waste Management
Facilities (IWMF) and the Civil Engineering and Development Department (CEDD)
South Cheung Chau Disposal Ground, high-speed craft plying in the vicinity
area, etc.
In certain circumstances, such as vessel
intrusions, emergency events and typhoons, the Duty Control Room Supervisor
will make contacts with the aforementioned government departments and/ or other
stakeholders for assistance.
An effective watch at the LNG Terminal shall be
continuously maintained and kept by the FSRU Terminal HK and SBV Operator with
round-the-clock communication channel via VHF, phone call, instant messaging
group chat and email as appropriate.
There will be communication checks throughout
the day. Regular drills and table top drill will take place in line with
terminal procedures and Full Mission Bridge Simulation (FMBS). These will
include activating of the Emergency Response teams within the HKLTL, FSRU
Terminal HK and SBV Operator. Third parties where appropriate will be invited
to attend and participate in drills.
To ensure the effective and efficient
communications are maintained between the HKLTL, FSRU Terminal HK, Authorities,
Stakeholders and Outsiders, the following means of communication will be used/
developed:
§ VHF
§ Phone Call
§ Instant Messaging Group Chat
§ Email
§ Establishment of regular coordination with
relevant stakeholders and Government departments including MD, FSD, Marpol,
Fill Management Division (FMD) of the CEDD, Agriculture, Fisheries and
Conservation Department (AFCD), EPD, IWMF, etc., to share and update marine
traffic information and emergency procedures;
§ Unavoidable transit through MCZ and/or incident
happening should be notified to the HKLTL as early as practical; for example,
traffic diversion owning to the reported obstruction, mechanical failure of
vessel and/or emergency incidents, etc.;
§ Owners, operators, masters, coxswains and
persons-in-charge of vessels requiring transit within the MCZ shall communicate
with the HKLTL by email or phone call; and
§ The HKLTL shall keep relevant stakeholders and
Government departments updated of any changes and/or updates on the
communication mechanism without delay.
An indicative flow chart of communication is
provided in Figure 6.4.
Before any craft is likely to enter the MCZ
without permission of the LNG Terminal, the SBVs must take the following
actions:
§ Try to establish contact with the vessel to
advise unauthorised vessel to alter course away from the MCZ
§ Manoeuvre the SBVs to a position between the
unauthorised vessel and the LNG Terminal
§ Contact Marpol if the unauthorised vessel
enters the SZ and does not take any avoiding action
The Master of the SBVs must not put his vessel
or the unauthorised vessel in any danger during manoeuvres. Communication with
the unauthorised vessel must be attempted using the following means:
§ Loud hailer
§ VHF (on Channel 16 for vessel locate outside HK
waters)
§ Vessel whistle
§ Aldis light
If communication is established the vessel must
be requested to leave the MCZ as soon as possible. If communication cannot be
established with unauthorised vessel or it refuses to leave the MCZ, any
suspicious activity or potential breaches of security at the LNG Terminal must
be immediately reported to:
§ Jetty CCR
§ HUD Control Room (for SBV’s operation)
§ MD
The unauthorised vessel will be escorted by a
SBV throughout the MCZ until finally clear.
The following must be contacted if any vessel
enters the 250m SZ:
§ Marpol (immediately)
§ Port Facility Security Officer (PFSO)/Deputy
PFSO (when time permits)
The Master of the SBVs can consider use of fire
monitors for drawing attention to the vessel or as a deterrent. Fire monitors
should not be directed in a manner which may impair the safe navigation or
reduce visibility of the unauthorized vessel. Consideration must be given to
the size and speed difference between unauthorised vessel and SBV to ensure the
SBV remains in a safe position at all times.
Any intrusions into the SZ or MCZ must be recorded
in a separate “Vessel Incursion Log” and capture the following information:
§ Vessel name / identity number
§ Date and time of entry and exit
§ What attempts were made to contact the
unauthorised vessel
§ Estimated Course and speed of the vessel
§ Which zone unauthorised vessel entered SZ or
MCZ or both
§ Indicate that photographs or CCTV are available
The Forward-Looking Infrared (FLIR) camera will
be equipped on SBV to capture a photograph of the vessel in low light
conditions. At the end of each watch the information from the Logbook must be
recorded into an excel spread sheet onboard the FSRU Vessel. The “Vessel
Incursion Log” may be presented as evidence to a higher authority in the event
of any dispute.
During adverse weather and met-ocean
conditions, it may be necessary for the FSRU Vessel and/or LNGC to depart from
the LNG Terminal. SBVs, harbour tugs and adequate port services will be
used for safe departure of the FSRU Vessel and LNGC to outside Hong Kong waters
for shelter. Assessments have been undertaken to simulate different
departure scenarios of emergency situations for adverse weather and met-ocean
conditions to ensure that vessels at the LNG Terminal can unberth and depart
safely in adverse met-ocean conditions, and in particular, tropical storms or
typhoons. The departure and timings of the departure for adverse weather
and met-ocean conditions will be determined in consultation between HKLTL, FSRU
Terminal HK, Jetty Lead, FSRU Vessel Master, HUD and relevant authorities (e.g.
MD) on case-by-case basis in relation to their potential severity.
HKLTL will have necessary arrangement to
conduct internal audits to review the effectiveness of the safety management
system. The audit will comply with international and Hong Kong regulatory
standards.
The Contractor is required to have necessary
arrangement to conduct internal audits to review the effectiveness of the
safety management system. The audit will comply with international and
Hong Kong regulatory standards. The Contractor will develop its own
mechanism or procedures of how and when audit is carried out. The
Contractor will have its own audit plan and submit to HKLTL for information.
The Contractor will implement internal audits annually and provide the
audit report for HKLTL’s information.
Apart from annual internal
audits, FSRU Terminal HK shall verify compliance of its IMS system at least
every twelve (12) months by way of an independent audit and submit the report
to HKLTL.
An audit
programme will be planned, taking into consideration the status and importance
of the processes and area to be audited, review procedures, results of previous
audits and prepare audit checklist. The audit criteria, scope and method
will be defined. The audit plan will be distributed to Management, the
Managers and all auditors. If required, external consultants or auditors
/ other external body can be used to audit and verify the system.
The auditing based on status and importance of
the activities will include observing, interviewing and assessing
representative samples of relevant documents and site inspection, etc. that
apply to the scope of the audit. Furthermore, they will assess the
overall adherence of the department’s day-to-day practices as per the Safety
Management System.
The effectiveness of the Safety Management
System will be verified through:
§ document checks;
§ physical condition tours; and
§ verification interviews.
In-depth document checks are usually performed
during or immediately after interviews with employees. Responses from the
auditees are substantiated by interviews with employees at various levels
and/or through physical condition verifications.
When the auditor’s report the non-conformances,
the concerned Manager is obliged to assess them objectively, and appropriate corrective/preventive
action shall be initiated as per Non-Conformance, Corrective & Preventive
Action procedure. An action plan will be developed by the Jetty SHEQ
Manager for the agreed action and the action holder shall be assigned. These
actions will be verified by the Auditor for proper closeout of the corrective
actions.
The observations, recommendations,
non-conformities and opportunities for improvement, resulting from internal
audits, reviews and interviews will be verified and re-evaluated for
effectiveness of the corrective action undertaken in the next scheduled audit
of the same scope. The Management Representative can initiate a re-audit,
depending on the importance of the issue, at any time.
FSRU Terminal HK shall hold a management
meeting annually to review the safety management system to ensure its
continuing suitability, adequacy and effectiveness. Processes are
reviewed for continuous improvement. Recommendations are implemented on
agreed timescale and the progresses are being monitored regularly.
The Jetty SHEQ Manager with association of
Management representative will be a qualified internal auditor to conduct each
internal audit. The auditor will be independent of the department
undergoing the audit. If applicable, an independent second auditor can be
used. The auditors will receive the appropriate auditor training course.
The safety review identifies the potential
higher risk associated with the task for further evaluation. All
non-conformance cases are registered and provided with a platform that record
all related investigation reports and associated follow up actions for tracking
and closure. FSRU Terminal HK shall follow Safety Observation Round
Procedure for conducting the safety review.
The performance against expectations, any
deviations from standards set in the procedures and policy, unsafe act and
conditions as well as unauthorized changes will be within the scope of the
safety audit. Regular review meeting with all involved parties is required to
monitor and ensure all investigation and follow up actions are conducted by its
assigned person/party within the required time frame.
([1])
Application for variation of an environmental permit for FEP-01/558/2018 was undertaken and the latest FEP
(FEP-01/558/2018/A) was issued on 6 November 2020.
([2])
Application for variation of an environmental permit for
FEP-03/558/2018/A was undertaken and the latest FEP (FEP-03/558/2018/B) was
issued on 25 August 2021.
([3])
Application for variation of an environmental permit for
FEP-02/558/2018 was undertaken and the latest FEP (FEP-02/558/2018/A) was
issued on 22 December 2020.
([4])
The South Cheung Chau Anchorage is established to facilitate the berthing of
vessels for efficient port operation. This new anchorage can also be used
by other vessels for contingency berthing when it is not used by LNG carriers.
([5])
For safety consideration, the FSRU Vessel needs to depart from the Jetty
to facilitate the maintenance work at the Jetty.
([6])
AIS is the short form of “automatic identification
system” which is an automatic tracking system that uses transceivers on ships
and is used by vessel traffic services (VTS). The AIS can provide real time
vessel information such as unique identification, position, course, and speed
to be displayed on a screen or an electronic chart display and information
system (ECDIS). AIS is intended to assist a vessel's watchstanding officers and
allow maritime authorities to track and monitor vessel movements.
([7])
The patrol launches of the MD are not built to be classed as
an intrinsically safe vessel; therefore, any request for MD’s assistance in
deploying patrol launches at or near the SZ would not be possibly conducted due
to gas safety consideration.
([8])
Vessel Traffic Centre (VTC) of MD would be able to advise participating vessels
not to enter, navigate through or anchor within the SZ, but it might not be
appropriate for VTC to give directions via VHF channel to prohibit
participating vessels from entering, navigating through or anchoring within the
SZ and/or MCZ if there does not exist any of the actual situation of vessel
traffic congestion, potential risk of collision, adverse weather, reduced
visibility or other hazardous conditions within the SZ and/or MCZ. Furthermore,
assistance from VTC may not be available if the vessel involved is a
non-participating local vessel.